SlideShare una empresa de Scribd logo
1 de 41
10 MW Solar PV Power Plant
Project Team : Nandhini | Nithya | Ragul Kannan | Sowparanika |Vignesh
10 MW Solar PV Power Plant
18/12/15 - Friday
 Project Description
 Objectives Involved
 Success Factors
 Appendix
Project Description
By installing and successfully operating 10 MW photovoltaic
(PV) power plants will deliver electricity for consumption by
the owners, the relevant peoples in the project assessment
place will be made aware of the technical and economic
potential of solar power generation. Furthermore, the power
required from the public grid will be reduced, and overall
expenditure on electric power will be lowered & our project
aims to create the necessary awareness among the
population, and especially among policymakers and large
investors,Youngsters.....
Objectives Involved
Overall project objective:
Our project will make a contribution toward sustainable energy
supply, and will serve as a showpiece demonstrating the
potential for stable and strongly desiring power supply based on
low-carbon energy production.
1. Schedule objectives
2. Permission objectives
3. Financial objectives
4. Technical objectives
5. Special objectives
1.Schedule objectives
Scheduling
 Total Project Time 5 Months
 Date of Ordering 2 Months
 Financial Closure Achievement 2 Months
 Plant & Machinery Ordering 1 Month
 DOO & FCA - During which detailed engineering, procurement, erection and
commissioning of civil & structural, mechanical and electrical equipment will be
executed.
 The plant & machinery ordering process will happen and the entire ordering
process will happen in one month. During this period, all detailed engineering
designs will be made ready for the execution phase to follow.
ACTIVITY DESCRIPTION PRECEEDING ACTIVITY DURATION (WEEKS)
A SITE ASSESSMENT - 1
B DESIGNING A 1
C LABOUR B 1
D PROCUREMENT B 6
E MOUNTING STRUCTURE (ERECTION) C,D 2
F PANEL ERECTION E 3
G JUNCTION BOX F 1
H INVERTER G 2
I CABLING G 1
J TRANSFORMER H,I 2
K COMMISSIONING J 1
1 2 3
A B
5
4
6
D
C
E
7
F
G
8 9 10
H
11
J
K
12
I
(1) (1) (1)
(2)(3)
(1)
(2) (1)
(2)
(1)
(2)
(6)
Dummy Activity
NETWORK DIAGRAM
Possible Pathways
A-B-C-E-F-G-H-J-K = 14 weeks
A-B-D-E-F-G-H-I-J-K =20 weeks
1 2 3
A B
5
4
6
D
C
E
7
F
G
8 9 10
H
11
J
K
12
I
(0,1) (1,2) (2,3)
(8,10)(10,13)
(13,14)
(14,16) (16,17)
(17,19)
(19,20)
(8,10)
(2,8)
Dummy Activity
PERT- FORWARD PASS METHOD
1 2 3
A B
5
4
6
D
C
E
7
F
G
8 9 10
H
11
J
K
12
I
(0,1) (1,2) (7,8)
(8,10)(10,13)
(13,14)
(14,16) (16,17)
(17,19)
(19,20)
(8,10)
(2,8)
Dummy Activity
PERT- BACKWARD PASS METHOD
1 2 3
A B
5
4
6
D
C
E
7
F
G
8 9 10
H
11
J
K
12
I
(1) (1) (1)
(2)(3)
(1)
(2) (1)
(2)
(1)
(2)
(6)
Dummy Activity
CRITICAL PATH
2.Permission objectives
Permissions/Clearances
Accredited by State Load Dispatch Centre
(SLDC)
for REC mechanism
Land purchase
Power Evacuation arrangement permission letter from Gov.
Confirmation of MeteringArrangement and location
Meter type, Manufacture, Model, Details for Energy Metering
Copy of PPA (important as Preferential PPA projects are not eligible for REC)
Proposed Model and make of plant equipment
Taking for compliance with the usage of fossil fuel criteria as specified by MNRE
Details of Connectivity with Gov. Grid
Connectivity Diagram and Single Line Diagram of Plant
Any other documents requested by State Gov.
Agreements
3.Financial objectives
Cost objectives
 PerWatt Rs.35 - 50
 Per MW Rs.3.5 - 4.0 Crore
 Per MW 4.5 - 5.0 Acre
 Per Acre Rs.25-40 Lakhs
 O&M Cost Rs.15 Lakhs/MW/Year
 Insurance 0.5% per year
 AD Benefit 4.21% per year
 Escalation Charges 2% every year
Year Loss Generation EB Tariff Amount
1 0.0066 11970000.0 7.00 83790000.0
2 0.0066 11890998.0 7.14 84901725.7
3 0.0066 11812517.4 7.28 86028201.8
4 0.0066 11734554.8 7.43 87169624.0
5 0.0066 11657106.7 7.58 88326190.6
6 0.0066 11580169.8 7.73 89498102.5
7 0.0066 11503740.7 7.88 90685563.3
8 0.0066 11427816.0 8.04 91888779.3
9 0.0066 11352392.4 8.20 93107959.7
10 0.0066 11277466.6 8.37 94343316.1
11 0.0066 11203035.4 8.53 95595063.2
12 0.0066 11129095.3 8.70 96863418.5
13 0.0066 11055643.3 8.88 98148602.3
14 0.0066 10982676.1 9.06 99450838.0
15 0.0066 10910190.4 9.24 100770351.7
16 0.0066 10838183.1 9.42 102107372.7
17 0.0066 10766651.1 9.61 103462133.4
18 0.0066 10695591.2 9.80 104834868.9
19 0.0066 10625000.3 10.00 106225818.0
20 0.0066 10554875.3 10.20 107635222.1
Year 20 years
Gen Units
Tariff 2% Es
Amt Rs
Payback Period
7Years -ve
Then +ve
Net Amount
Gen.Amount-Total
Expenses
Year Capital Cost -552000000 Cash Flow
1 -ve -486960000.00
2 -ve -420808274.28
3 -ve -353530072.46
4 -ve -285110448.46
5 -ve -215534257.89
6 -ve -144786155.43
7 -ve -72850592.14
8 +ve 288187.20
9 +ve 74646146.87
10 +ve 150239462.95
11 +ve 227084526.14
12 +ve 305197944.64
13 +ve 384596546.97
14 +ve 465297384.95
15 +ve 547317736.65
16 +ve 630675109.38
17 +ve 715387242.74
18 +ve 801472111.67
19 +ve 888947929.65
20 +ve 977833151.78
-₹ 0.60
-₹ 0.40
-₹ 0.20
₹ 0.00
₹ 0.20
₹ 0.40
₹ 0.60
₹ 0.80
₹ 1.00
₹ 1.20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
CAPITALCOST-INBILLIONS
Payback Period
-₹ 552,000,000.00 -₹ 552,000,000.00 Cash Flow
Levelized Cost of energy
10 years 15 years 20 years
Total Cost
739,500,000.00
739,500,000.00 833,250,000.00 927,000,000.00
Total Gen
116,206,762.60
116,206,762.60 171,487,403.06 224,967,704.22
Rs./unit ₹ 6.36 ₹ 4.86 ₹ 4.12
₹ 0.0
₹ 1.0
₹ 2.0
₹ 3.0
₹ 4.0
₹ 5.0
₹ 6.0
₹ 7.0
₹ 6.36
₹ 4.86
₹ 4.12
PERUNITCOST
NO.OFYEARS
LEVELIZED COST OF ENERGY
10 years 15 years 20 years
Bank loans for Solar PV Plant setup
2 kinds of Financing mechanisms
Recourse Financing
Non-Recourse Financing
Loan could be in the range of 40-60% project cost
CDM & REC Benefits
 REC Mechanism and CDM are mutually exclusive and hence a power
developer can claim CDM benefits (Carbon Credits) also.
 REC Principal Regulations, there is no lower limit for Solar Power
plants to be eligible for RECs. Though it previously stated that 250 KW
is the minimum size for plants to be eligible for RECs, the same has
been removed as part of the above stated amendment.
No Subsidy
Central Government through MNRE
 For systems Upto 100 kWp in size, Upto 15% subsidy can be
availed with the help of MNRE-empanelled channel
partners.
Solar Energy Corporation of India
 For systems of sizes 100 kWp-500 kWp, subsidy can be
availed through Solar Energy Corporation of India.
4.Technical objectives
On-Grid
Details
 Plant Capacity 10 MW
 Solar radiation 4-7 kWh/m2/day
 Hrs of operation/Day 5-7 Hrs
 Plant working days 300 Days
 Ave.annual Production 12.6 M.U (10*6*300 MWhr)
 Inverter Central Inverter
 Inside Losses 5 % from generation
Also calculate the Number of sunny days, DayTemperatures,Air Mass….etc
Site Assessment
 Prepare Plant Layout Surveying & Now using
Google Earth with ArcGIS
 Latitude 90-310
 Area of plant No's of modules (55 Acres)
 Available shadow area Waste land - Ground
 SoilType All Coarse / Fine Soils used
 Foundation 100 mm thickness
250 Wp - Panel Specifications
 Solar Panel Watt Peak 235 W
 ModuleType Standard
 Technology Mono crystalline
 Mounting Disposition Ground - Tilted
 Open circuit voltage 37V
 Short circuit current 8.6 A
 Max.Power voltage 30V
 Max.Power current 7.84 A
250 Wp - Panel
Design Calculation
Total Plant Size - 10 MW
Individual Sections - 500 kW * 20 Sets
No.of DC Cabinet - 560V * 20 Sets
No.of AC Cabinet - 380V * 20 Sets
No.of Inverters - 500 kVA * 20 Sets
No.of Junction Boxes - 560W * 320 Sets
Monitoring Devices - 1 Set
Protection Devices - 1 Set
Infrastructure - As required
Each 500 kW Set
PV Arrays - 16 Sets
Mounting Structure - 16 Sets
DC Junction Box (560W) - 16 Sets
DC Cabinet (560V) - 1 Set
Inverter (500 kVA) - 1 Set
AC Distribution Cabinet - 1 Set
15 PV Arrays - Has 8 Rows
Last PV Array - Has 5 Rows
Each Row - Has 16 Modules
Net Panels (500 kW) - (8*16) + (5*16) = 2000 Panels
Like 20 Sets (10 MW) - 20*2000 = 40000 Panels
PV Array – 16
500 kW - Design layout
PV Array 1
DCDistributionBox
ACDistributionBox
Inverter
Junction Box 1PV Array 1
Junction Box 2PV Array 2
Junction Box 3PV Array 3
Junction Box 4PV Array 4
Junction Box 5PV Array 5
Junction Box 6PV Array 6
Junction Box 7PV Array 7
Junction Box 8PV Array 8
Junction Box 9PV Array 9
Junction Box 10PV Array 10
Junction Box 11PV Array 11
Junction Box 12PV Array 12
Junction Box 13PV Array 13
Junction Box 14PV Array 14
Junction Box 15PV Array 15
Junction Box 16PV Array 16
10 MW Design layout
DISTRIBUTION
BOARD
₹ 0.00
₹ 20.00
₹ 40.00
₹ 60.00
₹ 80.00
₹ 100.00
₹ 120.00
9,500,000
10,000,000
10,500,000
11,000,000
11,500,000
12,000,000
12,500,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
AMOUNT-INMILLIONS
GENERATEDUNITS
NO.OFYEARS
SOLAR PV PLANT
Generation Amount
Amount of ele.pro/year 12600000 Units
CER 12600 Units
1 CER 1 Ton of Co2
1 CER 0.4 Euro
1 Euro 72 Rupees
Total CER (Euro) 5040 Euro
Total Value/Annum ₹ 362,880.00 Rupees
For 15 Years ₹ 5,443,200.00 Rupees
CER Calculation
5.Special objectives
Success Factors
For Output
 Plant Location
 Quality of equipment used
 SolarTracking systems
 O&M activities
For Project
 Satisfied clients
 Met project objectives
 Completed within budget
 Delivered on time
Our Project Pathway
Proposal
• November 6
Permission
• November 13
Financial
• November 20
Report
• Today
Appendix
 Tamilnadu Energy Development Agency (TEDA) Website
 Ministry of New & Renewable Energy (MNRE)Website
 Solar PV Systems – Chetan Singh Solanki
 Solar Electricity – Michel Boxwell

Más contenido relacionado

La actualidad más candente

1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and TrackingATUL RAJ
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuidePrivate Consultants
 
Optimisation of Balance of System (BOS) for Solar Projects
Optimisation of Balance of System (BOS) for Solar ProjectsOptimisation of Balance of System (BOS) for Solar Projects
Optimisation of Balance of System (BOS) for Solar ProjectsGensol Engineering Limited
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenanceLeonardo ENERGY
 
Solar Photovoltaic Power Plant
Solar Photovoltaic Power PlantSolar Photovoltaic Power Plant
Solar Photovoltaic Power PlantPratish Rawat
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantDr Naim R Kidwai
 
Developing Solar Projects
Developing Solar ProjectsDeveloping Solar Projects
Developing Solar Projectsalejolop
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
PV solar Design and Installtion
PV solar Design and InstalltionPV solar Design and Installtion
PV solar Design and InstalltionEli Israeli
 
Solar Power Plant System Sizing
Solar Power Plant System SizingSolar Power Plant System Sizing
Solar Power Plant System Sizingfirstgreen
 
Solar photovoltaic powerpoint
Solar photovoltaic powerpointSolar photovoltaic powerpoint
Solar photovoltaic powerpointWilliam Wallace
 
Design Calculations for Solar Water Heating System
Design Calculations for Solar Water Heating SystemDesign Calculations for Solar Water Heating System
Design Calculations for Solar Water Heating Systemsangeetkhule
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystsolpowerpeople
 
Solar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSolar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSlideTeam
 

La actualidad más candente (20)

Solar Power Plant Design and PV Syst
Solar Power Plant Design and PV SystSolar Power Plant Design and PV Syst
Solar Power Plant Design and PV Syst
 
1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
 
Optimisation of Balance of System (BOS) for Solar Projects
Optimisation of Balance of System (BOS) for Solar ProjectsOptimisation of Balance of System (BOS) for Solar Projects
Optimisation of Balance of System (BOS) for Solar Projects
 
Economics of Solar Park
Economics of Solar ParkEconomics of Solar Park
Economics of Solar Park
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
Solar rooftop presentation
Solar rooftop presentationSolar rooftop presentation
Solar rooftop presentation
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant Maintenance
 
Solar Photovoltaic Power Plant
Solar Photovoltaic Power PlantSolar Photovoltaic Power Plant
Solar Photovoltaic Power Plant
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plant
 
Developing Solar Projects
Developing Solar ProjectsDeveloping Solar Projects
Developing Solar Projects
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
PV solar Design and Installtion
PV solar Design and InstalltionPV solar Design and Installtion
PV solar Design and Installtion
 
Solar Power Plant System Sizing
Solar Power Plant System SizingSolar Power Plant System Sizing
Solar Power Plant System Sizing
 
Solar photovoltaic powerpoint
Solar photovoltaic powerpointSolar photovoltaic powerpoint
Solar photovoltaic powerpoint
 
Design Calculations for Solar Water Heating System
Design Calculations for Solar Water Heating SystemDesign Calculations for Solar Water Heating System
Design Calculations for Solar Water Heating System
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsyst
 
Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013
 
Solar power Plant
Solar power PlantSolar power Plant
Solar power Plant
 
Solar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation SlidesSolar Panel Installation Proposal PowerPoint Presentation Slides
Solar Panel Installation Proposal PowerPoint Presentation Slides
 

Destacado

Solar System proposal
Solar System proposalSolar System proposal
Solar System proposalSohail Azeem
 
Ruppur nuclear power plant
Ruppur nuclear power plantRuppur nuclear power plant
Ruppur nuclear power plantA. R. Atiq
 
Jaitapur nuclear power plant ppt
Jaitapur nuclear power plant pptJaitapur nuclear power plant ppt
Jaitapur nuclear power plant pptNikita Bhinde
 
Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaAkash Jauhari
 
Eai corporate presentation
Eai   corporate presentationEai   corporate presentation
Eai corporate presentationEAI
 
Solar product business plan
Solar product business planSolar product business plan
Solar product business planIndrajith Nair
 

Destacado (10)

Proposal desain
Proposal desainProposal desain
Proposal desain
 
RE 2022
RE 2022RE 2022
RE 2022
 
Solar System proposal
Solar System proposalSolar System proposal
Solar System proposal
 
Ruppur nuclear power plant
Ruppur nuclear power plantRuppur nuclear power plant
Ruppur nuclear power plant
 
Jaitapur nuclear power plant ppt
Jaitapur nuclear power plant pptJaitapur nuclear power plant ppt
Jaitapur nuclear power plant ppt
 
Solar pv systems
Solar pv systemsSolar pv systems
Solar pv systems
 
Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in India
 
Eai corporate presentation
Eai   corporate presentationEai   corporate presentation
Eai corporate presentation
 
Designing Solar PV Systems (Rooftops)
Designing Solar PV Systems(Rooftops)Designing Solar PV Systems(Rooftops)
Designing Solar PV Systems (Rooftops)
 
Solar product business plan
Solar product business planSolar product business plan
Solar product business plan
 

Similar a Project Proposal on 10 MW Solar PV Power Plant

Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Sayanti Sanyal
 
Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...
Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...
Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...Sayanti Sanyal
 
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine FarmsMichael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine FarmsJohn Blue
 
Design of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV SystemDesign of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV Systemsangeetkhule
 
Waterfall Turbine Development Primer - Updated
Waterfall Turbine Development Primer - UpdatedWaterfall Turbine Development Primer - Updated
Waterfall Turbine Development Primer - UpdatedJason Rota
 
Proposed Turbine Inlet Air Cooling for MLNG processing plant
Proposed Turbine Inlet Air Cooling for MLNG processing plantProposed Turbine Inlet Air Cooling for MLNG processing plant
Proposed Turbine Inlet Air Cooling for MLNG processing plantDato Mat Isa
 
Team+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 springTeam+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 springJaeho Jung
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportalatop007
 
The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...IrSOLaV Pomares
 
Power market operation 발표
Power market operation 발표Power market operation 발표
Power market operation 발표상진 정
 
Off Grid PV System
Off Grid PV SystemOff Grid PV System
Off Grid PV SystemDilawez Alam
 
Green Energy From Heat - Themo Electric Generation (TEG)
Green Energy From Heat  - Themo Electric Generation (TEG)Green Energy From Heat  - Themo Electric Generation (TEG)
Green Energy From Heat - Themo Electric Generation (TEG)jamietpe
 
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان... الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...Egyptian Engineers Association
 
Energetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaEnergetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaInsulin Angel
 
Dual Axis Solar Tracker Using Microcontroller
Dual Axis Solar Tracker Using MicrocontrollerDual Axis Solar Tracker Using Microcontroller
Dual Axis Solar Tracker Using MicrocontrollerIRJET Journal
 
Energy Production For Finance (1)
Energy Production For Finance (1)Energy Production For Finance (1)
Energy Production For Finance (1)AHMAD MUJTABA MALIK
 
IRJET - The Implementation of Arduino based Single Axis Solar Tracking Sy...
IRJET -  	  The Implementation of Arduino based Single Axis Solar Tracking Sy...IRJET -  	  The Implementation of Arduino based Single Axis Solar Tracking Sy...
IRJET - The Implementation of Arduino based Single Axis Solar Tracking Sy...IRJET Journal
 
Diesel generator rent service (long term) for Telecom Operator
Diesel generator rent service (long term) for Telecom OperatorDiesel generator rent service (long term) for Telecom Operator
Diesel generator rent service (long term) for Telecom OperatorOtgontugs Ulziisuren
 
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations Turlough Guerin GAICD FGIA
 

Similar a Project Proposal on 10 MW Solar PV Power Plant (20)

Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
 
Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...
Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...
Solar Energy Assessment Report for 100 kWp of Chandigarh, Punjab created by E...
 
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine FarmsMichael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
Michael Reese - Electric and Thermal Energy Strategies for Minnesota Swine Farms
 
Solar Training 20100208
Solar Training 20100208Solar Training 20100208
Solar Training 20100208
 
Design of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV SystemDesign of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV System
 
Waterfall Turbine Development Primer - Updated
Waterfall Turbine Development Primer - UpdatedWaterfall Turbine Development Primer - Updated
Waterfall Turbine Development Primer - Updated
 
Proposed Turbine Inlet Air Cooling for MLNG processing plant
Proposed Turbine Inlet Air Cooling for MLNG processing plantProposed Turbine Inlet Air Cooling for MLNG processing plant
Proposed Turbine Inlet Air Cooling for MLNG processing plant
 
Team+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 springTeam+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 spring
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transport
 
The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...The CECRE: Making renewable energy technologies compatible with the security ...
The CECRE: Making renewable energy technologies compatible with the security ...
 
Power market operation 발표
Power market operation 발표Power market operation 발표
Power market operation 발표
 
Off Grid PV System
Off Grid PV SystemOff Grid PV System
Off Grid PV System
 
Green Energy From Heat - Themo Electric Generation (TEG)
Green Energy From Heat  - Themo Electric Generation (TEG)Green Energy From Heat  - Themo Electric Generation (TEG)
Green Energy From Heat - Themo Electric Generation (TEG)
 
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان... الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 
Energetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaEnergetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and Tunisia
 
Dual Axis Solar Tracker Using Microcontroller
Dual Axis Solar Tracker Using MicrocontrollerDual Axis Solar Tracker Using Microcontroller
Dual Axis Solar Tracker Using Microcontroller
 
Energy Production For Finance (1)
Energy Production For Finance (1)Energy Production For Finance (1)
Energy Production For Finance (1)
 
IRJET - The Implementation of Arduino based Single Axis Solar Tracking Sy...
IRJET -  	  The Implementation of Arduino based Single Axis Solar Tracking Sy...IRJET -  	  The Implementation of Arduino based Single Axis Solar Tracking Sy...
IRJET - The Implementation of Arduino based Single Axis Solar Tracking Sy...
 
Diesel generator rent service (long term) for Telecom Operator
Diesel generator rent service (long term) for Telecom OperatorDiesel generator rent service (long term) for Telecom Operator
Diesel generator rent service (long term) for Telecom Operator
 
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
Clean Energy Council (CEC) Annual Conference 2015 Compiled Presentations
 

Más de Vignesh Sekar

Wind Power Generation Schemes
Wind Power Generation SchemesWind Power Generation Schemes
Wind Power Generation SchemesVignesh Sekar
 
Ultimate Analysis of Coal
Ultimate Analysis of CoalUltimate Analysis of Coal
Ultimate Analysis of CoalVignesh Sekar
 
Wastewater Recycling
Wastewater RecyclingWastewater Recycling
Wastewater RecyclingVignesh Sekar
 
Treated wastewater for Irrigation
Treated wastewater for IrrigationTreated wastewater for Irrigation
Treated wastewater for IrrigationVignesh Sekar
 
Systematic Roadmap Approach on Solar City
Systematic Roadmap Approach on Solar CitySystematic Roadmap Approach on Solar City
Systematic Roadmap Approach on Solar CityVignesh Sekar
 
Plastic Waste Management and Recycling Technology : P2
Plastic Waste Management and Recycling Technology : P2Plastic Waste Management and Recycling Technology : P2
Plastic Waste Management and Recycling Technology : P2Vignesh Sekar
 
Plastic Waste Management and Recycling Technology : P1
Plastic Waste Management and Recycling Technology : P1Plastic Waste Management and Recycling Technology : P1
Plastic Waste Management and Recycling Technology : P1Vignesh Sekar
 
Mass and Flow duration curves
Mass and Flow duration curvesMass and Flow duration curves
Mass and Flow duration curvesVignesh Sekar
 
Industrial energy auditing and reporting
Industrial energy auditing and reportingIndustrial energy auditing and reporting
Industrial energy auditing and reportingVignesh Sekar
 
Direct and Bending stresses
Direct and Bending stressesDirect and Bending stresses
Direct and Bending stressesVignesh Sekar
 
Delineation and Comparison of Urban Heat Islands in Tamilnadu
Delineation and Comparison of Urban Heat Islands in TamilnaduDelineation and Comparison of Urban Heat Islands in Tamilnadu
Delineation and Comparison of Urban Heat Islands in TamilnaduVignesh Sekar
 
Applications of GIS in Public Health Engineering
Applications of GIS in Public Health EngineeringApplications of GIS in Public Health Engineering
Applications of GIS in Public Health EngineeringVignesh Sekar
 
Applications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementApplications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementVignesh Sekar
 

Más de Vignesh Sekar (14)

Wind Power Generation Schemes
Wind Power Generation SchemesWind Power Generation Schemes
Wind Power Generation Schemes
 
Ultimate Analysis of Coal
Ultimate Analysis of CoalUltimate Analysis of Coal
Ultimate Analysis of Coal
 
Wastewater Recycling
Wastewater RecyclingWastewater Recycling
Wastewater Recycling
 
Treated wastewater for Irrigation
Treated wastewater for IrrigationTreated wastewater for Irrigation
Treated wastewater for Irrigation
 
Systematic Roadmap Approach on Solar City
Systematic Roadmap Approach on Solar CitySystematic Roadmap Approach on Solar City
Systematic Roadmap Approach on Solar City
 
Plastic Waste Management and Recycling Technology : P2
Plastic Waste Management and Recycling Technology : P2Plastic Waste Management and Recycling Technology : P2
Plastic Waste Management and Recycling Technology : P2
 
Plastic Waste Management and Recycling Technology : P1
Plastic Waste Management and Recycling Technology : P1Plastic Waste Management and Recycling Technology : P1
Plastic Waste Management and Recycling Technology : P1
 
Mass and Flow duration curves
Mass and Flow duration curvesMass and Flow duration curves
Mass and Flow duration curves
 
Industrial energy auditing and reporting
Industrial energy auditing and reportingIndustrial energy auditing and reporting
Industrial energy auditing and reporting
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
 
Direct and Bending stresses
Direct and Bending stressesDirect and Bending stresses
Direct and Bending stresses
 
Delineation and Comparison of Urban Heat Islands in Tamilnadu
Delineation and Comparison of Urban Heat Islands in TamilnaduDelineation and Comparison of Urban Heat Islands in Tamilnadu
Delineation and Comparison of Urban Heat Islands in Tamilnadu
 
Applications of GIS in Public Health Engineering
Applications of GIS in Public Health EngineeringApplications of GIS in Public Health Engineering
Applications of GIS in Public Health Engineering
 
Applications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementApplications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste Management
 

Último

Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Último (20)

Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Project Proposal on 10 MW Solar PV Power Plant

  • 1. 10 MW Solar PV Power Plant Project Team : Nandhini | Nithya | Ragul Kannan | Sowparanika |Vignesh
  • 2. 10 MW Solar PV Power Plant 18/12/15 - Friday  Project Description  Objectives Involved  Success Factors  Appendix
  • 3. Project Description By installing and successfully operating 10 MW photovoltaic (PV) power plants will deliver electricity for consumption by the owners, the relevant peoples in the project assessment place will be made aware of the technical and economic potential of solar power generation. Furthermore, the power required from the public grid will be reduced, and overall expenditure on electric power will be lowered & our project aims to create the necessary awareness among the population, and especially among policymakers and large investors,Youngsters.....
  • 4. Objectives Involved Overall project objective: Our project will make a contribution toward sustainable energy supply, and will serve as a showpiece demonstrating the potential for stable and strongly desiring power supply based on low-carbon energy production. 1. Schedule objectives 2. Permission objectives 3. Financial objectives 4. Technical objectives 5. Special objectives
  • 6. Scheduling  Total Project Time 5 Months  Date of Ordering 2 Months  Financial Closure Achievement 2 Months  Plant & Machinery Ordering 1 Month  DOO & FCA - During which detailed engineering, procurement, erection and commissioning of civil & structural, mechanical and electrical equipment will be executed.  The plant & machinery ordering process will happen and the entire ordering process will happen in one month. During this period, all detailed engineering designs will be made ready for the execution phase to follow.
  • 7. ACTIVITY DESCRIPTION PRECEEDING ACTIVITY DURATION (WEEKS) A SITE ASSESSMENT - 1 B DESIGNING A 1 C LABOUR B 1 D PROCUREMENT B 6 E MOUNTING STRUCTURE (ERECTION) C,D 2 F PANEL ERECTION E 3 G JUNCTION BOX F 1 H INVERTER G 2 I CABLING G 1 J TRANSFORMER H,I 2 K COMMISSIONING J 1
  • 8. 1 2 3 A B 5 4 6 D C E 7 F G 8 9 10 H 11 J K 12 I (1) (1) (1) (2)(3) (1) (2) (1) (2) (1) (2) (6) Dummy Activity NETWORK DIAGRAM
  • 9. Possible Pathways A-B-C-E-F-G-H-J-K = 14 weeks A-B-D-E-F-G-H-I-J-K =20 weeks
  • 10. 1 2 3 A B 5 4 6 D C E 7 F G 8 9 10 H 11 J K 12 I (0,1) (1,2) (2,3) (8,10)(10,13) (13,14) (14,16) (16,17) (17,19) (19,20) (8,10) (2,8) Dummy Activity PERT- FORWARD PASS METHOD
  • 11. 1 2 3 A B 5 4 6 D C E 7 F G 8 9 10 H 11 J K 12 I (0,1) (1,2) (7,8) (8,10)(10,13) (13,14) (14,16) (16,17) (17,19) (19,20) (8,10) (2,8) Dummy Activity PERT- BACKWARD PASS METHOD
  • 12. 1 2 3 A B 5 4 6 D C E 7 F G 8 9 10 H 11 J K 12 I (1) (1) (1) (2)(3) (1) (2) (1) (2) (1) (2) (6) Dummy Activity CRITICAL PATH
  • 14. Permissions/Clearances Accredited by State Load Dispatch Centre (SLDC) for REC mechanism
  • 15. Land purchase Power Evacuation arrangement permission letter from Gov. Confirmation of MeteringArrangement and location Meter type, Manufacture, Model, Details for Energy Metering Copy of PPA (important as Preferential PPA projects are not eligible for REC) Proposed Model and make of plant equipment Taking for compliance with the usage of fossil fuel criteria as specified by MNRE Details of Connectivity with Gov. Grid Connectivity Diagram and Single Line Diagram of Plant Any other documents requested by State Gov. Agreements
  • 17. Cost objectives  PerWatt Rs.35 - 50  Per MW Rs.3.5 - 4.0 Crore  Per MW 4.5 - 5.0 Acre  Per Acre Rs.25-40 Lakhs  O&M Cost Rs.15 Lakhs/MW/Year  Insurance 0.5% per year  AD Benefit 4.21% per year  Escalation Charges 2% every year
  • 18. Year Loss Generation EB Tariff Amount 1 0.0066 11970000.0 7.00 83790000.0 2 0.0066 11890998.0 7.14 84901725.7 3 0.0066 11812517.4 7.28 86028201.8 4 0.0066 11734554.8 7.43 87169624.0 5 0.0066 11657106.7 7.58 88326190.6 6 0.0066 11580169.8 7.73 89498102.5 7 0.0066 11503740.7 7.88 90685563.3 8 0.0066 11427816.0 8.04 91888779.3 9 0.0066 11352392.4 8.20 93107959.7 10 0.0066 11277466.6 8.37 94343316.1 11 0.0066 11203035.4 8.53 95595063.2 12 0.0066 11129095.3 8.70 96863418.5 13 0.0066 11055643.3 8.88 98148602.3 14 0.0066 10982676.1 9.06 99450838.0 15 0.0066 10910190.4 9.24 100770351.7 16 0.0066 10838183.1 9.42 102107372.7 17 0.0066 10766651.1 9.61 103462133.4 18 0.0066 10695591.2 9.80 104834868.9 19 0.0066 10625000.3 10.00 106225818.0 20 0.0066 10554875.3 10.20 107635222.1 Year 20 years Gen Units Tariff 2% Es Amt Rs
  • 19. Payback Period 7Years -ve Then +ve Net Amount Gen.Amount-Total Expenses Year Capital Cost -552000000 Cash Flow 1 -ve -486960000.00 2 -ve -420808274.28 3 -ve -353530072.46 4 -ve -285110448.46 5 -ve -215534257.89 6 -ve -144786155.43 7 -ve -72850592.14 8 +ve 288187.20 9 +ve 74646146.87 10 +ve 150239462.95 11 +ve 227084526.14 12 +ve 305197944.64 13 +ve 384596546.97 14 +ve 465297384.95 15 +ve 547317736.65 16 +ve 630675109.38 17 +ve 715387242.74 18 +ve 801472111.67 19 +ve 888947929.65 20 +ve 977833151.78
  • 20. -₹ 0.60 -₹ 0.40 -₹ 0.20 ₹ 0.00 ₹ 0.20 ₹ 0.40 ₹ 0.60 ₹ 0.80 ₹ 1.00 ₹ 1.20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 CAPITALCOST-INBILLIONS Payback Period -₹ 552,000,000.00 -₹ 552,000,000.00 Cash Flow
  • 21. Levelized Cost of energy 10 years 15 years 20 years Total Cost 739,500,000.00 739,500,000.00 833,250,000.00 927,000,000.00 Total Gen 116,206,762.60 116,206,762.60 171,487,403.06 224,967,704.22 Rs./unit ₹ 6.36 ₹ 4.86 ₹ 4.12
  • 22. ₹ 0.0 ₹ 1.0 ₹ 2.0 ₹ 3.0 ₹ 4.0 ₹ 5.0 ₹ 6.0 ₹ 7.0 ₹ 6.36 ₹ 4.86 ₹ 4.12 PERUNITCOST NO.OFYEARS LEVELIZED COST OF ENERGY 10 years 15 years 20 years
  • 23. Bank loans for Solar PV Plant setup 2 kinds of Financing mechanisms Recourse Financing Non-Recourse Financing Loan could be in the range of 40-60% project cost
  • 24. CDM & REC Benefits  REC Mechanism and CDM are mutually exclusive and hence a power developer can claim CDM benefits (Carbon Credits) also.  REC Principal Regulations, there is no lower limit for Solar Power plants to be eligible for RECs. Though it previously stated that 250 KW is the minimum size for plants to be eligible for RECs, the same has been removed as part of the above stated amendment.
  • 25. No Subsidy Central Government through MNRE  For systems Upto 100 kWp in size, Upto 15% subsidy can be availed with the help of MNRE-empanelled channel partners. Solar Energy Corporation of India  For systems of sizes 100 kWp-500 kWp, subsidy can be availed through Solar Energy Corporation of India.
  • 28. Details  Plant Capacity 10 MW  Solar radiation 4-7 kWh/m2/day  Hrs of operation/Day 5-7 Hrs  Plant working days 300 Days  Ave.annual Production 12.6 M.U (10*6*300 MWhr)  Inverter Central Inverter  Inside Losses 5 % from generation Also calculate the Number of sunny days, DayTemperatures,Air Mass….etc
  • 29. Site Assessment  Prepare Plant Layout Surveying & Now using Google Earth with ArcGIS  Latitude 90-310  Area of plant No's of modules (55 Acres)  Available shadow area Waste land - Ground  SoilType All Coarse / Fine Soils used  Foundation 100 mm thickness
  • 30. 250 Wp - Panel Specifications  Solar Panel Watt Peak 235 W  ModuleType Standard  Technology Mono crystalline  Mounting Disposition Ground - Tilted  Open circuit voltage 37V  Short circuit current 8.6 A  Max.Power voltage 30V  Max.Power current 7.84 A
  • 31. 250 Wp - Panel
  • 32. Design Calculation Total Plant Size - 10 MW Individual Sections - 500 kW * 20 Sets No.of DC Cabinet - 560V * 20 Sets No.of AC Cabinet - 380V * 20 Sets No.of Inverters - 500 kVA * 20 Sets No.of Junction Boxes - 560W * 320 Sets Monitoring Devices - 1 Set Protection Devices - 1 Set Infrastructure - As required
  • 33. Each 500 kW Set PV Arrays - 16 Sets Mounting Structure - 16 Sets DC Junction Box (560W) - 16 Sets DC Cabinet (560V) - 1 Set Inverter (500 kVA) - 1 Set AC Distribution Cabinet - 1 Set 15 PV Arrays - Has 8 Rows Last PV Array - Has 5 Rows Each Row - Has 16 Modules Net Panels (500 kW) - (8*16) + (5*16) = 2000 Panels Like 20 Sets (10 MW) - 20*2000 = 40000 Panels PV Array – 16
  • 34. 500 kW - Design layout PV Array 1 DCDistributionBox ACDistributionBox Inverter Junction Box 1PV Array 1 Junction Box 2PV Array 2 Junction Box 3PV Array 3 Junction Box 4PV Array 4 Junction Box 5PV Array 5 Junction Box 6PV Array 6 Junction Box 7PV Array 7 Junction Box 8PV Array 8 Junction Box 9PV Array 9 Junction Box 10PV Array 10 Junction Box 11PV Array 11 Junction Box 12PV Array 12 Junction Box 13PV Array 13 Junction Box 14PV Array 14 Junction Box 15PV Array 15 Junction Box 16PV Array 16
  • 35. 10 MW Design layout DISTRIBUTION BOARD
  • 36. ₹ 0.00 ₹ 20.00 ₹ 40.00 ₹ 60.00 ₹ 80.00 ₹ 100.00 ₹ 120.00 9,500,000 10,000,000 10,500,000 11,000,000 11,500,000 12,000,000 12,500,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 AMOUNT-INMILLIONS GENERATEDUNITS NO.OFYEARS SOLAR PV PLANT Generation Amount
  • 37. Amount of ele.pro/year 12600000 Units CER 12600 Units 1 CER 1 Ton of Co2 1 CER 0.4 Euro 1 Euro 72 Rupees Total CER (Euro) 5040 Euro Total Value/Annum ₹ 362,880.00 Rupees For 15 Years ₹ 5,443,200.00 Rupees CER Calculation
  • 39. Success Factors For Output  Plant Location  Quality of equipment used  SolarTracking systems  O&M activities For Project  Satisfied clients  Met project objectives  Completed within budget  Delivered on time
  • 40. Our Project Pathway Proposal • November 6 Permission • November 13 Financial • November 20 Report • Today
  • 41. Appendix  Tamilnadu Energy Development Agency (TEDA) Website  Ministry of New & Renewable Energy (MNRE)Website  Solar PV Systems – Chetan Singh Solanki  Solar Electricity – Michel Boxwell