6. Factors Influencing the Quality of Estimates 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) People Quality of Estimates Project Duration Project Structure and Organization Padding Estimates Organization Culture Other (Nonproject) Factors Planning Horizon
7.
8.
9. Macro versus Micro Estimating 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) TABLE 5.1 Conditions for Preferring Top-Down or Bottom-Up Time and Cost Estimates Condition Macro Estimates Micro Estimates (Top-down) (Bottom-up) Strategic decision making X Cost and time important X High uncertainty X Internal, small project X Fixed-price contract X Customer wants details X Unstable scope X
10.
11.
12. Apportion Method of Allocating Costs Using the WBS 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) FIGURE 5.1
13. Simplified Basic Function Point Count Process for a Prospective Project or Deliverable 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) TABLE 5.2
14. Example: Function Point Count Method 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) TABLE 5.3
15.
16. SB45 Support Cost Estimate Worksheet 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) FIGURE 5.2
17. Phase Estimating over Product Life Cycle 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) FIGURE 5.3
18.
19.
20. Types of Costs Direct Costs Project Overhead Costs General & Administrative Overhead Costs 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson)
21.
22.
23.
24. Contract Bid Summary Costs 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) FIGURE 5.6 Direct costs $80,000 Direct overhead $20,000 G&A overhead (20%) $20,000 Profit (20%) $24,000 Total bid $144,000
25. Three Views of Cost 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) FIGURE 5.5
26.
27.
28.
29. Creating a Database for Estimating 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) FIGURE 5.7 Estimating Database Templates
30. Key Terms 10/01/07 SJSU - Bus. 286 David Bentley (Gray & Larson) Apportionment methods Bottom-up estimates Contingency funds Delphi method Direct costs Function points Interaction costs Learning curves Overhead costs Padding estimates Phase estimating Ratio methods Template method Time and cost databases Top-down estimates