SlideShare una empresa de Scribd logo
1 de 35
Vogtle Units 3 & 4 Nuclear Development
Early Site Construction Progression
Mike Jordan
New Nuclear Projects-Engineering/Construction
May 1, 2013
2
Vogtle Plant – Units 3 & 4
FAST FACTS
• Two Nuclear Generating Units
• Capacity – 1117 MW Per Unit
• Operator – Southern Nuclear
• Technology - Westinghouse AP1000
• Constructor – CBI (formerly Shaw)
• Located in Burke County Near
Waynesboro, Ga.
• Size – Approximately 1800 Acres
3
Vogtle 3 & 4 Timeline
4
Vogtle 3 & 4 – Initial Site Work
JULY 2009
5
Vogtle 3 & 4 Site Layout
•Lay down & Storage area
Modular
Assembly
Building
•Containment
Vessel FAB Area
•Units 3 & 4
Nuclear
Islands
•Cooling Towers
Foundations
•Fabrication &
Laydown Area
•Parking &
Offices
•Units 1 & 2
January 2013
6
Initial Construction Activities
• Clearing, grubbing, excavation, backfill, grading, and
dewatering
• Install temporary and permanent access roads and
drainage features
• Install temporary facilities – office trailers, change shacks,
underground electrical, water, fiber, laydown areas, and
concrete batch plant
• Set up site security – guard houses, fences, access gates,
badging facilities, etc.
• Build warehouses, offices, and Training/Simulator Building
• Relocate 500 kv transmission line interferences
7
Plant Area Earthwork Progress
October 2009
8
Plant Area Earthwork Progress
October 2009
9
Plant Area Earthwork Progress
January 2010
10
Plant Area Earthwork Progress
March 2010
11
Plant Area Earthwork Progress
March 2010
12
Plant Area Earthwork Progress
December 2010
13
Early Plant Major Construction Activities
• Complete Mechanically Stabilized Earth (MSE) wall, mud
mat, and concrete basemat for the Nuclear Island
• Install 10 ft diameter Circulating Water Piping
• Install Turbine Building foundations
• Erect 13 story Modular Assembly Building
• Install foundations for and erect 1M Ton O Crane
• Fabricate 140 ft diameter Containment Vessel bottom head
• Install foundations for 560 ft tall Cooling Towers
14
Plant Area Progress
March 2011
15
Plant Area Progress
March 2011
16
Plant Area Progress
March 2011
17
Key Components/Facilities Progress
July 2011
18
July 2011
Key Components/Facilities Progress
19
Key Components/Facilities Progress
July 2011
20
Aerial Photo - Plant Area
August 2011
21
January 2012
Key Components Progress
22
January 2012
Key Components Progress
23
Key Components Progress
January 2012
24
Key Components Progress
July 2012
25
Key Components Progress
July 2012
26
Key Components Progress
July 2012
27
Key Components Progress
January 2013
28
Key Components Progress
January 2013
29
Key Components Progress
January 2013
30
1ST
Nuclear Concrete
• Nuclear Island Basemat is the foundation for the Reactor
Containment Building and the Reactor Auxiliary Building
and is the first safety related concrete placement
• Nuclear Island Basemat is six (6) foot thick and contains
over 6800 cubic yards of concrete
• This placement of concrete was rehearsed during a 1/6
size “mock-up” in September 2012 to ensure a successful
continuous pour
• The actual placement was delayed several months due to
rebar discrepancies in the design and final resolution
with the NRC
• In March 2013 the full size Nuclear Island Basemat was
placed successfully in approximately 51 hours
31
1st
Nuclear Concrete Major Milestone
Unit 3 Nuclear Island Basemat Placement
March 2013
32
Some of the Facts
• Over 22 million cubic yards of earth were moved during
excavation and backfill while preparing the site for
construction
• The Nuclear Island area was excavated to a depth of
approximately 80 ft to remove unsuitable marl material and
replaced with Class I backfill
• The 70,000 square foot Simulator/Training Center took 1
year to complete and currently houses all operator training
activities
• The 13 story Modular Assembly Building is over 300 ft long
and is where structural modules are assembled and loaded
on heavy haul transporters for moving to the appropriate
plant location
• There are 23,000 tons of steel, 16M feet of cable, and 546,00
ft of piping associated with the two units
• There are currently over 2200 workers on site and the peak
workforce will be around 5000
33
Vogtle 3 & 4 Site Layout
•Lay down & Storage area
Modular
Assembly
Building
•Containment
Vessel FAB Area
•Units 3 & 4
Nuclear
Islands
•Cooling Towers
Foundations
•Fabrication &
Laydown Area
•Parking &
Offices
•Units 1 & 2
January 2013
34
Any Questions
35

Más contenido relacionado

La actualidad más candente

Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Crosstown TO
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Crosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
RDS WYCO - Install overview 2018
RDS WYCO -  Install overview 2018RDS WYCO -  Install overview 2018
RDS WYCO - Install overview 2018Jon Boutilier
 
Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Darren Shaw, SIOR
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Brittany Maxwell
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATION7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATIONMark Johnston
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Crosstown TO
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCrosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Crosstown TO
 

La actualidad más candente (20)

Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
RDS WYCO - Install overview 2018
RDS WYCO -  Install overview 2018RDS WYCO -  Install overview 2018
RDS WYCO - Install overview 2018
 
Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATION7311 STEVENS CROFT PRESENTATION
7311 STEVENS CROFT PRESENTATION
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank Station
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017Cedarvale & Forest Hill Stations Open House - November 2017
Cedarvale & Forest Hill Stations Open House - November 2017
 

Destacado

Aula 5 contabilida financiera.
Aula 5   contabilida financiera.Aula 5   contabilida financiera.
Aula 5 contabilida financiera.familiapop
 
Soal teori ekonomi
Soal teori ekonomiSoal teori ekonomi
Soal teori ekonomiyubz fahreza
 
V Jornada Didáctica de Español organizada por Högskolan Dalarna, Suecia
V Jornada Didáctica de Español organizada por Högskolan Dalarna, SueciaV Jornada Didáctica de Español organizada por Högskolan Dalarna, Suecia
V Jornada Didáctica de Español organizada por Högskolan Dalarna, SueciaMario López Cordero
 
Red Social Toonix
Red Social Toonix Red Social Toonix
Red Social Toonix yessica2719
 
Umj wawasan komunikasi bisnis
Umj   wawasan komunikasi bisnisUmj   wawasan komunikasi bisnis
Umj wawasan komunikasi bisnisyuls1423
 
Mobile advertising mena bpg bates slides & deloitte tmt may 2013
Mobile advertising mena bpg bates slides & deloitte tmt   may 2013Mobile advertising mena bpg bates slides & deloitte tmt   may 2013
Mobile advertising mena bpg bates slides & deloitte tmt may 2013Grégory Bolle
 
Random acts of kindness
Random acts of kindnessRandom acts of kindness
Random acts of kindnessJudith Coulson
 

Destacado (12)

Aula 5 contabilida financiera.
Aula 5   contabilida financiera.Aula 5   contabilida financiera.
Aula 5 contabilida financiera.
 
2
22
2
 
Modelos de equipamiento
Modelos de equipamientoModelos de equipamiento
Modelos de equipamiento
 
Id letters in_zakat
Id letters in_zakatId letters in_zakat
Id letters in_zakat
 
Soal teori ekonomi
Soal teori ekonomiSoal teori ekonomi
Soal teori ekonomi
 
V Jornada Didáctica de Español organizada por Högskolan Dalarna, Suecia
V Jornada Didáctica de Español organizada por Högskolan Dalarna, SueciaV Jornada Didáctica de Español organizada por Högskolan Dalarna, Suecia
V Jornada Didáctica de Español organizada por Högskolan Dalarna, Suecia
 
Red Social Toonix
Red Social Toonix Red Social Toonix
Red Social Toonix
 
CASLA
CASLACASLA
CASLA
 
Umj wawasan komunikasi bisnis
Umj   wawasan komunikasi bisnisUmj   wawasan komunikasi bisnis
Umj wawasan komunikasi bisnis
 
Mobile advertising mena bpg bates slides & deloitte tmt may 2013
Mobile advertising mena bpg bates slides & deloitte tmt   may 2013Mobile advertising mena bpg bates slides & deloitte tmt   may 2013
Mobile advertising mena bpg bates slides & deloitte tmt may 2013
 
Dmobi Games
Dmobi GamesDmobi Games
Dmobi Games
 
Random acts of kindness
Random acts of kindnessRandom acts of kindness
Random acts of kindness
 

Similar a K.2 vogtle units 3 and 4 nuclear development early site construction progression

Earth House Field Building Process
Earth House Field Building ProcessEarth House Field Building Process
Earth House Field Building ProcessTimo Kettunen
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2David Matthew
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyThorne & Derrick International
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Crosstown TO
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Into infinity (Onkalo Project)
Into infinity (Onkalo Project)Into infinity (Onkalo Project)
Into infinity (Onkalo Project)Jagriti Mandal
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbourFHRahman1
 
Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind Niamh McGrath
 
PROJECT-List_Attach_A_Jim Benge 6-14
PROJECT-List_Attach_A_Jim Benge 6-14PROJECT-List_Attach_A_Jim Benge 6-14
PROJECT-List_Attach_A_Jim Benge 6-14Jim Benge
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Crosstown TO
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Crosstown TO
 
PIS Obajana - Cement Factory
PIS Obajana - Cement FactoryPIS Obajana - Cement Factory
PIS Obajana - Cement FactorySven Maedler
 

Similar a K.2 vogtle units 3 and 4 nuclear development early site construction progression (20)

Earth House Field Building Process
Earth House Field Building ProcessEarth House Field Building Process
Earth House Field Building Process
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2
 
2014 CRW - Omega Morgan Rigging Job of the Year
2014 CRW - Omega Morgan Rigging Job of the Year2014 CRW - Omega Morgan Rigging Job of the Year
2014 CRW - Omega Morgan Rigging Job of the Year
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Into infinity (Onkalo Project)
Into infinity (Onkalo Project)Into infinity (Onkalo Project)
Into infinity (Onkalo Project)
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind Neart na Gaoithe Offshore Wind
Neart na Gaoithe Offshore Wind
 
PROJECT-List_Attach_A_Jim Benge 6-14
PROJECT-List_Attach_A_Jim Benge 6-14PROJECT-List_Attach_A_Jim Benge 6-14
PROJECT-List_Attach_A_Jim Benge 6-14
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018
 
072014_Bunker Mentality
072014_Bunker Mentality072014_Bunker Mentality
072014_Bunker Mentality
 
PIS Obajana - Cement Factory
PIS Obajana - Cement FactoryPIS Obajana - Cement Factory
PIS Obajana - Cement Factory
 
Burj khalifa Dubai
Burj khalifa DubaiBurj khalifa Dubai
Burj khalifa Dubai
 
Summer training
Summer trainingSummer training
Summer training
 

Más de ascemiami-dade

Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...ascemiami-dade
 
3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...ascemiami-dade
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvementsascemiami-dade
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectascemiami-dade
 
2.4 fll airport improvements
2.4 fll airport improvements2.4 fll airport improvements
2.4 fll airport improvementsascemiami-dade
 
3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...ascemiami-dade
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvementsascemiami-dade
 
3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...ascemiami-dade
 
3.2 wpb transit village
3.2 wpb transit village3.2 wpb transit village
3.2 wpb transit villageascemiami-dade
 
3.3 everglades restoration plans
3.3 everglades restoration plans3.3 everglades restoration plans
3.3 everglades restoration plansascemiami-dade
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal linkascemiami-dade
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal linkascemiami-dade
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel ceiascemiami-dade
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoirascemiami-dade
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoirascemiami-dade
 

Más de ascemiami-dade (20)

Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
 
3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvements
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
2.4 fll airport improvements
2.4 fll airport improvements2.4 fll airport improvements
2.4 fll airport improvements
 
3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvements
 
4 public policy panel
4   public policy panel4   public policy panel
4 public policy panel
 
3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...
 
4 cards
4   cards4   cards
4 cards
 
3.2 wpb transit village
3.2 wpb transit village3.2 wpb transit village
3.2 wpb transit village
 
3.3 everglades restoration plans
3.3 everglades restoration plans3.3 everglades restoration plans
3.3 everglades restoration plans
 
3 climate change
3   climate change3   climate change
3 climate change
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal link
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal link
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel cei
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir
 
2 transportation
2   transportation2   transportation
2 transportation
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir
 
1.3 pbcwud update
1.3 pbcwud update1.3 pbcwud update
1.3 pbcwud update
 

Último

Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Nikki Chapple
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesManik S Magar
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxfnnc6jmgwh
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024TopCSSGallery
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observabilityitnewsafrica
 
Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Kaya Weers
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Hiroshi SHIBATA
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructureitnewsafrica
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 

Último (20)

Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
 
Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 

K.2 vogtle units 3 and 4 nuclear development early site construction progression

  • 1. Vogtle Units 3 & 4 Nuclear Development Early Site Construction Progression Mike Jordan New Nuclear Projects-Engineering/Construction May 1, 2013
  • 2. 2 Vogtle Plant – Units 3 & 4 FAST FACTS • Two Nuclear Generating Units • Capacity – 1117 MW Per Unit • Operator – Southern Nuclear • Technology - Westinghouse AP1000 • Constructor – CBI (formerly Shaw) • Located in Burke County Near Waynesboro, Ga. • Size – Approximately 1800 Acres
  • 3. 3 Vogtle 3 & 4 Timeline
  • 4. 4 Vogtle 3 & 4 – Initial Site Work JULY 2009
  • 5. 5 Vogtle 3 & 4 Site Layout •Lay down & Storage area Modular Assembly Building •Containment Vessel FAB Area •Units 3 & 4 Nuclear Islands •Cooling Towers Foundations •Fabrication & Laydown Area •Parking & Offices •Units 1 & 2 January 2013
  • 6. 6 Initial Construction Activities • Clearing, grubbing, excavation, backfill, grading, and dewatering • Install temporary and permanent access roads and drainage features • Install temporary facilities – office trailers, change shacks, underground electrical, water, fiber, laydown areas, and concrete batch plant • Set up site security – guard houses, fences, access gates, badging facilities, etc. • Build warehouses, offices, and Training/Simulator Building • Relocate 500 kv transmission line interferences
  • 7. 7 Plant Area Earthwork Progress October 2009
  • 8. 8 Plant Area Earthwork Progress October 2009
  • 9. 9 Plant Area Earthwork Progress January 2010
  • 10. 10 Plant Area Earthwork Progress March 2010
  • 11. 11 Plant Area Earthwork Progress March 2010
  • 12. 12 Plant Area Earthwork Progress December 2010
  • 13. 13 Early Plant Major Construction Activities • Complete Mechanically Stabilized Earth (MSE) wall, mud mat, and concrete basemat for the Nuclear Island • Install 10 ft diameter Circulating Water Piping • Install Turbine Building foundations • Erect 13 story Modular Assembly Building • Install foundations for and erect 1M Ton O Crane • Fabricate 140 ft diameter Containment Vessel bottom head • Install foundations for 560 ft tall Cooling Towers
  • 20. 20 Aerial Photo - Plant Area August 2011
  • 30. 30 1ST Nuclear Concrete • Nuclear Island Basemat is the foundation for the Reactor Containment Building and the Reactor Auxiliary Building and is the first safety related concrete placement • Nuclear Island Basemat is six (6) foot thick and contains over 6800 cubic yards of concrete • This placement of concrete was rehearsed during a 1/6 size “mock-up” in September 2012 to ensure a successful continuous pour • The actual placement was delayed several months due to rebar discrepancies in the design and final resolution with the NRC • In March 2013 the full size Nuclear Island Basemat was placed successfully in approximately 51 hours
  • 31. 31 1st Nuclear Concrete Major Milestone Unit 3 Nuclear Island Basemat Placement March 2013
  • 32. 32 Some of the Facts • Over 22 million cubic yards of earth were moved during excavation and backfill while preparing the site for construction • The Nuclear Island area was excavated to a depth of approximately 80 ft to remove unsuitable marl material and replaced with Class I backfill • The 70,000 square foot Simulator/Training Center took 1 year to complete and currently houses all operator training activities • The 13 story Modular Assembly Building is over 300 ft long and is where structural modules are assembled and loaded on heavy haul transporters for moving to the appropriate plant location • There are 23,000 tons of steel, 16M feet of cable, and 546,00 ft of piping associated with the two units • There are currently over 2200 workers on site and the peak workforce will be around 5000
  • 33. 33 Vogtle 3 & 4 Site Layout •Lay down & Storage area Modular Assembly Building •Containment Vessel FAB Area •Units 3 & 4 Nuclear Islands •Cooling Towers Foundations •Fabrication & Laydown Area •Parking & Offices •Units 1 & 2 January 2013
  • 35. 35