3. Rehabilitation/Replacement Analysis
1. PROJECT BACKGROUND
2. ROUTE ALTERNATIVE EVALUATION
3. DATA COLLECTION
4. DATA ANALYSIS & EVALUATION
5. INSTALLATION & CONSTRUCTABILITY
6. EVALUATION MATRIX
7. REHAB EVALUATION
4. 1. Project Background
Understand the basis/objective of the project
Familiarize w/ history of the line
Operational constraints
Recognize stakeholder concerns
Sliplined
5. 2. Route Alternate Evaluation
Jurisdiction considerations
Mitigating community impacts
Shut down limitations
Economical solution
7. 3. Data Collection
Collect existing utility and underground facility records
Review recent available aerial photography
Perform site visits of preliminary pipe alignments
Identify potential profile conflicts
Catalogue special jurisdictional requirements
8. 3. Data Collection
Geotechnical report
Pipe Laying Schedule
Plat information
9. 4. Data Analysis & Evaluation
EXISTING UTILITY IDENTIFICATION AND
VERIFICATION
Utility Contact Table
Obtained “as-built” information from utility companies
Utility Company
Letter Sent
ATT ‐ Miami‐Dade
5/3/2013
Response
Received
5/7/2013
5/3/2013
4/8/2013
City of North Miami
5/3/2013
4/22/2013
City of North Miami Beach Public Utilities
5/3/2013
5/29/2013
City of Opalocka
5/3/2013
Pending
Comcast Cable
Reviewed possible route corridors to identified existing
utilities along corridors
ATT ‐ Miami‐Dade
5/3/2013
6/26/2013
Florida Department of Transportation
5/3/2013
5/9/2013
Florida City Gas
5/3/2013
5/8/2013
FPL
5/3/2013
5/21/2013
FPL Fibernet LLC
5/3/2013
6/25/2013
MCI
5/3/2013
4/16/2013
Miami Dade Water Sewer
N/A
5/21/2013
MDC Public Works
5/3/2013
5/14/2013
Teco Peoples Gas
5/3/2013
4/19/2013
American Traffic Solutions
St From NE
Ave
Ave and NE
Ave
5/22/2013
5/3/2013
6/25/2013
5/3/2013
6/25/2013
XO Communications
Typical Section along NE
5/3/2013
Systems Integration & Maintenance INC
10th
5/7/2013
City of Miami Gardens
6th
5/6/2013
5/3/2013
Level 3 Communications LLC
159th
5/3/2013
Florida Gas Transmission Company
5/3/2013
Pending
Typical Section along NE 159th St From NE 3rd Ave and NE 4th Ave
10. 4. Data Analysis & Evaluation
ENVIRONMENTAL EVALUATIONS
Goal – avoid, minimize and mitigate/address
potential project impacts and
Level-I contamination assessment;
Re-evaluating the site prior to
replacements/replacements
11. 4. Data Analysis & Evaluation
DESIGN CRITERIA FOR REPLACEMENTS
In‐line Plug Valves
every 0.5 mile
ARV
installed at all high points and other intermediate points
MANHOLES
every 1,200 feet and at valves and closures
PRESSURES
Working pressure : 100 PSI , Test pressure : 150 PSI
VELOCITY
5 FPS MAX
PIPE FRICTION FACTOR
Hazen Williams “ C “ Factor: 120, 140 preferable
HYDRAULIC CAPACITY
equivalence of a 72‐inch diameter
12. 4. Data Analysis & Evaluation
PIPE MATERIALS EVALUATION
Client Preferences and Familiarity
Ease of Installation
Installation Under Water
Corrosion Resistance
Production Quality Control
System Flexibility
Hydraulic Efficiency
Manufacture & Availability
Surge Protection
Performance within environment
Cost
Type
Size (inches)
Polyvinyl Chloride (PVC)
14‐48
High Density Polyethylene (HDPE)
½‐63
Ductile Iron (DIP)
4‐64
Pre‐Stressed Concrete Cylinder (PCCP)
10‐144
Bar Wrap Concrete Cylinder
10‐144
Fiberglass Reinforced Pipe (FRP)
12‐96
Steel
24‐144
13. 4. Data Analysis & Evaluation
PIPE MATERIALS EVALUATION
Advantages
PCCP
Steel Pipe
Durability and competitive prices for large diameter
Competitive price for large diameter pipes
Lighter than concrete pipes
Disadvantages
Unit weight per foot is the highest of alternatives.
Corrosion control measures will be required
Installation of pipes will be new experience for local
contractors. Corrosion control measures will be required
Does agency have experience and familiarity with this
pipe
FRP
Excellent corrosion resistance
DIP
Flexibility for future connections
Relatively easy to install because of mechanical/push‐ Corrosion control measures will be required
on joints
HDPE
Longer trenches (access pits/shafts) to be opened at a
Leak resistance over PCCP due to quantity of joints &
time
more leak proof joints
Work zone/lay down area requirements
15. 5. Installation & Constructability
Installation performance of proposed pipe
material
Coordination with Agencies for street
closures
Construction rates
Impacts to community (Church, Schools,
Hospitals…)
Trenchless construction for major highways
& other critical crossings
Pipeline
16. 5. Installation & Constructability
MAINTENANCE OF TRAFFIC:
• Lane closure limits
• Total road closure requirements
• Mayor issues with necessary detours
along thoroughfares
17. 6. Evaluation Matrix
Evaluation Parameter
Weight Factor
Minimize adverse traffic impacts (MOT)
7
Minimize public agency coordination/permitting
7
Low impact on businesses and/or public facilities/stakeholders
2
Risk of Successful Construction
5
Laterals/ Bends/ Obstructions/ Retrains
8
Future Redevelopment
2
Minimize Impact to Schedule
10
Minimize ROW or easement acquisition
2
Minimize project cost (OPC)
10
19. 7. Rehab Evaluation
Identify & assess viability of available
rehabilitation methods
Evaluate rehabilitate or replacement
Rehab
Replace
20. 7. Rehab Evaluation
Accessibility & site constraints
Soil conditions
Magnitude of flows
Available bypassing or rerouting flows
Mechanism of failure or problem
Rights-of-way
Lateral connections
Length and size of pipeline
Need for up-sizing line
21. 7. Rehab & Evaluation
CHOOSING THE RIGHT METHOD
Identify acceptable level of risk
Define shut down parameters
Plan out requirements
27. 7. Rehab Evaluation
DESIGN CRITERIA FOR REHABILITATION
PRESSURES
Working pressure : 60‐65 PSI , Test pressure : 70 PSI
STRUCTURAL FUNCTIONALITY
Class IV
VELOCITY
5 FPS MAX
PIPE FRICTION FACTOR
Hazen Williams “ C “ Factor: 140 preferable
HYDRAULIC CAPACITY
equivalence of a 72‐inch diameter
30. 7. Rehab Evaluation
A number of rehabilitation methods could be examined
Condition of existing pipe
Cost
Track record
Drop in capacity associated with the reduction of cross-sectional
Feasibility and practicality limit number of rehabilitation methods
31. 7. Rehab Evaluation
Booster Pump Stations may need to be reconfigured or shutdown
FM bypass associated with Pump Station
35. PROCUREMENT METHODS EVALUATION
DESIGN-BID-BUILD (DBB)
PROGRESSIVE DESIGN BUILD
CONSTRUCTION MANAGER AT RISK (CMR)
DESIGN-BUILD (DB)
Traditional DB
Design-build-operate
Design-build-finance-operate
Design-build-own-operate-transfer
DESIGN‐BID‐BUILD
CMAR
PROGRESSIVE DB
DESIGN BUILD
DBO
DBOOT
DBFO
PROJECT DELIVERY SPECTRUM
36. PROCUREMENT METHODS EVALUATION
DESIGN-BID-BUILD (DBB)
Separate contracts for design and construction.
OWNER
Design documents are 100% complete
Contractor selection is based entirely on cost.
DESIGNER
BUILDER
Contracts
Communication
37. PROCUREMENT METHODS EVALUATION
Select Design‐ Builder
PROGRESSIVE DESIGN BUILD
30%
Design
Procurement process in a short timeframe
Project can be implemented in phases
OWNER
VE
Maximizes owner flexibility
Initially cost for construction is not known
60%
Design
DB ENTITY
Cost is determined through combination of
negotiated and competitive processes
TRADE
SUBS
Contracts
Communication
Constructability
Review
90%
Design
Constructability
Review
Submit/Approve
LS / GMP
38. PROCUREMENT METHODS EVALUATION
CONSTRUCTION MANAGER AT RISK (CMR)
CMR handles some aspects of design
Designer and CMR hold separate contracts with owner;
OWNER
CMR contracts directly with trades and takes on
“performance risk”
CMR
Overlapping design and construction
Professional management to an owner whose
TRADE
SUBS
DESIGNER
organization may not have capabilities
Facilitates phased construction
Constructability and speed of implementation
Contracts
Communication
39. PROCUREMENT METHODS EVALUATION
TRADITIONAL DESIGN-BUILD (DB)
Design and construction services in same contract.
Single point of responsibility
OWNER
Typically multi-step procurement process
Owner transfer of responsibility; DB entity is liable
DB ENTITY
for design and construction
Overlapping design (~30%) and construction
DESIGNER
BUILDER
Contracts
Communication
40. BID PROCESS
D/CM/DB
TEAM
CONSTRUCTION ENGINEERING (POST-DESIGN PHASE)
Construction Administration
FINAL CONTRACT
DOCUMENTS
• Pre-Bid Documents
AGENCY
PROGRAM
MANAGER
Review of Final Contract Documents.
Project Advertisement and Bid Documents
Distribution
• Pre-Bid Conference.
RISK
MANAGEMENT
PROCUREMENT
ATTORNEY’S
OFFICE
WRITTEN
COMMENTS
WRITTEN
COMMENTS
WRITTEN
COMMENTS
• Preparation and Issuance of Addenda
PROGRAM
MANAGER
• Bid Opening and Award
• Preparation of As-Bid Contract Documents
Construction Management
MEETINGS AS NECESSARY
D/CM/DB
TEAM
FINAL BID
DOCUMENTS