SlideShare una empresa de Scribd logo
1 de 41
Descargar para leer sin conexión
PROGRAM MANAGEMENT
|
ENGINEERING
|
PLANNING

SELECTION AND IMPLEMENTATION OF DELIVERY
METHODS FOR REHABILITATION/REPLACEMENT OF
WASTEWATER SYSTEMS
November 14, 2013
AGENDA
 REPLACEMENT / REHABILITATION ANALYSIS
 PROCUREMENT METHODS EVALUATION
 BID / CONTRACT DOCUMENTS
 BID PROCESS
Rehabilitation/Replacement Analysis
1. PROJECT BACKGROUND
2. ROUTE ALTERNATIVE EVALUATION
3. DATA COLLECTION
4. DATA ANALYSIS & EVALUATION
5. INSTALLATION & CONSTRUCTABILITY
6. EVALUATION MATRIX
7. REHAB EVALUATION
1. Project Background





Understand the basis/objective of the project
Familiarize w/ history of the line
Operational constraints
Recognize stakeholder concerns

Sliplined
2. Route Alternate Evaluation





Jurisdiction considerations
Mitigating community impacts
Shut down limitations
Economical solution
2. Route Alternate Evaluation
ALIGNMENT VARIATIONS
3. Data Collection
 Collect existing utility and underground facility records
 Review recent available aerial photography
 Perform site visits of preliminary pipe alignments
 Identify potential profile conflicts
 Catalogue special jurisdictional requirements
3. Data Collection
 Geotechnical report
 Pipe Laying Schedule
 Plat information
4. Data Analysis & Evaluation
EXISTING UTILITY IDENTIFICATION AND
VERIFICATION

Utility Contact Table

 Obtained “as-built” information from utility companies

Utility Company

Letter Sent

ATT ‐ Miami‐Dade

5/3/2013

Response 
Received
5/7/2013

5/3/2013

4/8/2013

City of North Miami

5/3/2013

4/22/2013

City of North Miami Beach Public Utilities

5/3/2013

5/29/2013

City of Opalocka

5/3/2013

Pending

Comcast Cable

 Reviewed possible route corridors to identified existing
utilities along corridors

ATT ‐ Miami‐Dade

5/3/2013

6/26/2013

Florida Department of Transportation

5/3/2013

5/9/2013

Florida City Gas

5/3/2013

5/8/2013

FPL

5/3/2013

5/21/2013

FPL Fibernet LLC

5/3/2013

6/25/2013

MCI

5/3/2013

4/16/2013

Miami Dade Water Sewer

N/A

5/21/2013

MDC Public Works

5/3/2013

5/14/2013

Teco Peoples Gas

5/3/2013

4/19/2013

American Traffic Solutions

St From NE
Ave

Ave and NE

Ave

5/22/2013

5/3/2013

6/25/2013

5/3/2013

6/25/2013

XO Communications
Typical Section along NE

5/3/2013

Systems Integration & Maintenance INC

10th

5/7/2013

City of Miami Gardens

6th

5/6/2013

5/3/2013

Level 3 Communications LLC

159th

5/3/2013

Florida Gas Transmission Company

5/3/2013

Pending

Typical Section along NE 159th St From NE 3rd Ave and NE 4th Ave
4. Data Analysis & Evaluation
ENVIRONMENTAL EVALUATIONS
 Goal – avoid, minimize and mitigate/address
potential project impacts and
 Level-I contamination assessment;
 Re-evaluating the site prior to
replacements/replacements
4. Data Analysis & Evaluation
DESIGN CRITERIA FOR REPLACEMENTS
In‐line Plug Valves 

every 0.5 mile

ARV

installed at all high points and other intermediate points

MANHOLES

every 1,200 feet and at valves and closures

PRESSURES

Working pressure : 100 PSI  , Test pressure : 150 PSI

VELOCITY

5 FPS MAX

PIPE FRICTION FACTOR

Hazen Williams “ C “ Factor: 120, 140 preferable

HYDRAULIC CAPACITY

equivalence of a 72‐inch diameter 
4. Data Analysis & Evaluation
PIPE MATERIALS EVALUATION
 Client Preferences and Familiarity
 Ease of Installation
 Installation Under Water
 Corrosion Resistance
 Production Quality Control
 System Flexibility
 Hydraulic Efficiency
 Manufacture & Availability
 Surge Protection
 Performance within environment
 Cost

Type

Size (inches)

Polyvinyl Chloride (PVC)

14‐48

High Density Polyethylene (HDPE)

½‐63

Ductile Iron (DIP)

4‐64

Pre‐Stressed Concrete Cylinder (PCCP)

10‐144

Bar Wrap Concrete Cylinder

10‐144

Fiberglass Reinforced Pipe (FRP)

12‐96

Steel

24‐144
4. Data Analysis & Evaluation
PIPE MATERIALS EVALUATION
Advantages
PCCP

Steel Pipe

Durability and competitive prices for large diameter

Competitive price for large diameter pipes 
Lighter than concrete pipes

Disadvantages
Unit weight per foot is the highest of alternatives.
Corrosion control measures will be required
Installation of pipes will be new experience for local 
contractors. Corrosion control measures will be required
Does agency have experience and familiarity with this 
pipe

FRP

Excellent corrosion resistance

DIP

Flexibility for future connections
Relatively easy to install because of mechanical/push‐ Corrosion control measures will be required
on joints

HDPE

Longer trenches (access pits/shafts) to be opened at a 
Leak resistance over PCCP due to quantity of joints & 
time
more leak proof joints
Work zone/lay down area requirements
4. Data Analysis & Evaluation
PIPE MATERIALS EVALUATION
PIPE MATERIALS EVALUATION MATRIX
Evaluation Criteria 
Most Desired Option 1 
Less Desired Option 3

Cost 63/64‐inch $/LF
1. Present Worth Capital Cost (PWCC)
PWCC Weighted Sub‐Total
1. Agency Experience and Familiarity
2. Connection to existing lines
3. Contractor's familiarit with pipe system
4. Pipe Laying length 
5. Pipe weight
6. Pipe joint flexibility
7. Pipe installation in groundwater
8. Internal corrosion resistance 
9. Cathodic Protection / Soil Corrosivity
10. Useful Life Span (Min. 50 Years)
11. Failure Characteristics
12. Diameter
Non‐Economical Average = Sfactors / 12
Non‐Economical Weighted

Pipe Material 
PCCP
Economical Factors
490
3
1.5
Non‐Economical Factors
1
1
1
2
3
3
2
2
2
2
3
1
1.9
0.2

Total Economical and Non‐Economical Weighted Factors
Ranking of Alternatives

1.7
2

Steel Pipe

DIP

FRP

340
2
1

460
3
1.5

279
1
0.5

3
3
3
1
1
1
2
3
3
2
1
1
2.0
1.0

2
2
2
2
2
2
1
3
3
2
2
2
2.1
1.0

3
3
3
1
1
2
2
1
1
1
1
1
1.7
0.8

2
3

2.5
4

1.3
1
5. Installation & Constructability
 Installation performance of proposed pipe
material
 Coordination with Agencies for street
closures
 Construction rates
 Impacts to community (Church, Schools,
Hospitals…)
 Trenchless construction for major highways
& other critical crossings
Pipeline
5. Installation & Constructability
MAINTENANCE OF TRAFFIC:

• Lane closure limits
• Total road closure requirements
• Mayor issues with necessary detours
along thoroughfares
6. Evaluation Matrix
Evaluation Parameter

Weight Factor

Minimize adverse traffic impacts (MOT)

7

Minimize public agency coordination/permitting

7

Low impact on businesses and/or public facilities/stakeholders

2

Risk of Successful Construction

5

Laterals/ Bends/ Obstructions/ Retrains

8

Future Redevelopment

2

Minimize Impact to Schedule

10

Minimize ROW or easement acquisition

2

Minimize project cost (OPC)

10
6. Evaluation Matrix

Location
Segment I
Segment II
Segment III
Segment IV‐A
Segment IV‐B
Segment V

Length (ft)
4,445 
1,535 
1,535 
1,535 
3,030 
4,405 
5,535 
4,560 
2,950 
3,210 
2,315 
2,090 
1,325 
1,380 
1,325 
1,350 
4,030 
3,995 
4,295 
4,640 
3,375 
2,605 
2,630 
3,950 

Routes /           
Weighting Factor
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4

7
0
3
3
3
2
3
1
3
2
3
1
1
2
3
1
0
1
3
2
2
0
3
2
1

7
0
21
21
21
14
21
7
21
14
21
7
7
14
21
7
0
7
21
14
14
0
21
14
7

3
0
0
0
0
2
1
2
2
3
2
2
1
2
1
1
2
0
2
1
2
3
2
2

5
21
0
0
0
0
14
7
14
14
21
14
14
7
14
7
7
14
0
14
7
14
21
14
14

0
3
3
3
2
3
1
3
2
1
2
2
3
2
1
1
2
0
0
2
1
1
1
0

5
0
15
15
15
10
15
5
15
10
5
10
10
15
10
5
5
10
0
0
10
5
5
5
0

0
3
3
3
0
2
1
1
2
3
1
1
1
3
2
1
2
3
1
1
1
3
3
1

8
0
15
15
15
0
10
5
5
10
15
5
5
5
15
10
5
10
15
5
5
5
15
15
5

0
3
3
3
2
3
0
0
1
3
1
0
0
3
0
2
3
3
2
1
0
3
2
0

2
0
24
24
24
16
24
0
0
8
24
8
0
0
24
0
16
24
24
16
8
0
24
16
0

3
0
0
0
1
3
1
2
1
1
2
3
1
0
2
2
2
2
1
1
1
3
2
1

10
6
0
0
0
2
6
2
4
2
2
4
6
2
0
4
4
4
4
2
2
2
6
4
2

0
3
3
3
2
3
1
1
2
3
2
1
0
2
0
1
2
3
1
1
1
3
2
2

2
0
30
30
30
20
30
10
10
20
30
20
10
0
20
0
10
20
30
10
10
10
30
20
20

0
3
3
3
0
3
1
2
0
2
2
0
1
3
1
2
1
2
1
1
2
3
3
0

Preferred
Alternate

Total Points

Minimize Project 
Cost (OPC)

Cost per Option

Minimize ROW or 
Easement 
Acquisition

Minimize Impact 
to Schedule

Future 
Redevelopment

Laterals/ Bends/ 
Obstructions/ 
Retrains

Risk of Successful 
Construction

Minimize public 
agency 
coordination / 
permitting
Low Impact on 
Businesses and/or 
Public Facilities / 
Stakeholders

Evaluation 
Parameters

Route 1
Route 2
Route 3
Route 4

Minimize Adverse 
Traffic Impact 
(MOT)

NEW PIPE MATRIX

10
0
6
6
6
0
6
2
4
0
4
4
0
2
6
2
4
2
4
2
2
4
6
6
0

$8,472,100
$3,510,600
$3,510,600
$3,510,600
$6,973,600
$11,198,100
$10,941,300
$9,178,200
$5,578,000
$5,879,000
$4,377,700
$4,007,900
$2,711,700
$2,738,800
$2,709,400
$2,828,200
$7,458,400
$7,330,500
$7,912,400
$8,588,700
$6,310,400
$5,583,200
$5,093,800
$7,302,300

0
3
3
3
3
0
2
1
1
0
2
3
1
3
2
0
1
3
2
0
1
1
3
0

0
30
30
30
30
0
20
10
10
0
20
30
10
30
20
0
10
30
20
0
10
10
30
0

27
141
141
141
92
126
58
83
88
122
92
82
55
140
55
51
101
128
83
58
50
138
124
48

.

.

.

.

.

.
7. Rehab Evaluation
 Identify & assess viability of available
rehabilitation methods
 Evaluate rehabilitate or replacement

Rehab

Replace
7. Rehab Evaluation
 Accessibility & site constraints
 Soil conditions
 Magnitude of flows
 Available bypassing or rerouting flows
 Mechanism of failure or problem
 Rights-of-way
 Lateral connections
 Length and size of pipeline
 Need for up-sizing line
7. Rehab & Evaluation
CHOOSING THE RIGHT METHOD
 Identify acceptable level of risk
 Define shut down parameters
 Plan out requirements
7. Rehab & Evaluation
7. Rehab & Evaluation
CIP REHABILITATION
7. Rehab & Evaluation
STEEL LINER SECTIONS
7. Rehab & Evaluation
SLIPLINING
7. Rehab & Evaluation
INTERNAL JOINT SEALS
7. Rehab Evaluation

DESIGN CRITERIA FOR REHABILITATION
PRESSURES

Working pressure : 60‐65 PSI  , Test pressure : 70 PSI

STRUCTURAL FUNCTIONALITY

Class IV

VELOCITY

5 FPS MAX

PIPE FRICTION FACTOR

Hazen Williams “ C “ Factor: 140 preferable

HYDRAULIC CAPACITY

equivalence of a 72‐inch diameter 
7. Rehab Evaluation
Problem
Definition

Capacity
Deficiencies

System 
Problem
Caused 
by 
excessive 
I/I

Problem 
Location

Structural
Condition

Size
Impact
Increase 
in pipe 
size 
required

No

Yes

Collapse 
has 
occurred 
or is 
eminent

Yes

At a 
Sewer 
Pipe

Yes
Full Replacement
1,2
No

Yes

Structure
Deficiencies

Appropriate
Options

No

Structural 
Rehabilitation
1,2,3,4
Non‐Structural 
Rehabilitation
5,6

No

Yes

Separate
Joint(s)

Yes

Offset 
Joint(s)

No

Joint Repair/ 
Pipe
Rehabilitation
1,5,6,7

Pipe 
Replacement
1

Joint Repair/
Grouting
7,8,9

Available
Technologies
Replacements
New Alignment
1 Open Cut
2 Microtunneling
Existing Alignment
1 Open Cut

Structural Reline
3 CIPP
4 Sliplining
Non‐Structural Reline
5 CIPP
6 Sliplining
Others
7 Mechanical joints
8 Chemical Grouting/Grouting
9 Cement Patching
7. Rehab Evaluation
 Sliplining
• Segmental Sliplining
• Continuous Sliplining
• Short Pipe
 Cured-In-Place (CIP) Lining
• Conventional CIP
• Composite CIP
 Grout-in-Place (GIP)
 StrongPIPE™ Hybrid FRP - Continuous Reinforced Composite
Liner
7. Rehab Evaluation
 A number of rehabilitation methods could be examined
 Condition of existing pipe
 Cost
 Track record
 Drop in capacity associated with the reduction of cross-sectional
 Feasibility and practicality limit number of rehabilitation methods
7. Rehab Evaluation
 Booster Pump Stations may need to be reconfigured or shutdown
 FM bypass associated with Pump Station
7. Rehab Evaluation
Identify Pipe Performance Issues 
(i.e.,  Flow Issues, Corrosion)
Would rehabbed line deliver required performance? 
If yes, proceed.  If no, then replace.

Pipe is structurally sound

Pipe is structurally inadequate

Pipe has infiltration issues or early 
signs of deterioration

Identify cause of structural deterioration 
and select semi‐structural/ 
structural rehab system

Pipe has infiltration issues

Pipe has early signs of deterioration

Identify cause of leakage and 
select non‐structural/ 
semi‐structural rehab system

Identify cause and select non‐structural  /semi‐
structural rehab system
CONSULTANT’S EVALUATION MATRIX
SPECIFIC PROJECT PARAMETERS:
 Minimize adverse traffic impacts (MOT)
 Minimize public agency coordination /
permitting
 Low Impact on Businesses and/or Public
Facilities / Stakeholders
 Risk of Successful Construction
 Laterals/ Bends/ Obstructions/ Retrains
 Future Redevelopment
 Minimize Impact to Schedule
 Reliance on Host Pipe Condition
 Flow Diversion Requirements
 Infiltration Concerns (During Construction)
 Reduction in Capacity
 Minimize Project Cost (OPC)
8

2

10

2

5

10

3

10

Open Trench 

0

0

0

0

0

0

3

15

3

24

3

6

0

0

3

6

0

0

3

15

3

30

2

14

2

14

3

15

2

10

2

16

2

4

1

10

3

6

1

3

3

15

0

0

CIPP

1,530 

HDPE Sliplining

3

21

1

7

3

15

1

5

0

0

0

0

3

30

1

2

1

3

1

5

2

20

Fiberglass Sliplining (Short Pipe)

Segment I

2

14

1

7

2

10

1

5

0

0

0

0

2

20

2

4

1

3

2

10

1

10

Open Trench 

Segment II

2

14

1

7

0

0

2

10

3

24

3

6

0

0

3

6

0

0

3

15

3

30

HDPE Sliplining

3

21

3

21

3

15

3

15

2

16

3

6

1

10

3

6

1

3

3

15

0

0

CIPP

4,410 

2

14

1

7

2

10

1

5

0

0

2

4

3

30

1

2

1

3

1

5

2

20

Fiberglass Sliplining (Short Pipe)

7

1

7

2

10

1

5

0

0

2

4

2

20

2

4

1

3

2

10

1

10

0

0

0

0

0

0

3

15

3

24

3

6

0

0

3

6

3

9

3

15

3

30

HDPE Sliplining

1

7

1

7

3

15

2

10

2

16

2

4

1

10

3

6

1

3

1

5

0

0

CIPP

3,177 

1

Open Trench 

Segment III

2

14

1

7

2

10

0

0

0

0

0

0

3

30

2

4

1

3

2

10

2

20

Fiberglass Sliplining (Short Pipe)

21

1

7

1

5

1

5

0

0

0

0

2

20

1

2

1

3

3

15

1

10

0

0

0

0

0

0

2

10

3

24

3

6

0

0

3

6

3

9

3

15

3

30

HDPE Sliplining

1

7

2

14

2

10

3

15

2

16

2

4

1

10

3

6

1

3

1

5

0

0

CIPP

1,367 

3

Open Trench 

Segment IV‐A

3

21

1

7

3

15

1

5

0

0

0

0

3

30

1

2

1

3

1

5

2

20

Fiberglass Sliplining (Short Pipe)

14

3

15

0

0

0

0

0

0

2

20

2

4

1

3

3

15

1

10

0

0

0

0

2

10

3

24

3

6

0

0

3

6

3

9

3

15

3

30

HDPE Sliplining

0

0

0

0

1

5

2

10

2

16

2

4

1

10

3

6

1

3

1

5

0

0

3

21

3

21

3

15

1

5

0

0

0

0

3

30

1

2

1

3

2

10

2

20

2

14

2

14

2

10

1

5

0

0

0

0

2

20

2

4

1

3

3

15

1

10

Open Trench 

2,470 

2

0

Fiberglass Sliplining (Short Pipe)

Segment V

14

0

CIPP

4,070 

2

Open Trench 

Segment IV‐B

Preferred Alternate

Minimize Impact to 
Schedule

5

Total Points

Future Redevelopment

5

Minimize Project Cost 
(OPC)

Laterals/ Bends/ 
Obstructions/ Retrains

7

Cost per Option

Risk of Successful 
Construction

7

Reduction in Capacity

Low Impact on 
Businesses and/or Public 
Facilities / Stakeholders

Rehabilitation Option 
Weighting Factor

Infiltration Concerns 
(During Construction)

Minimize public agency 
coordination / permitting

Length 
(ft.)

Minimize Adverse Traffic 
Impact (MOT)

Location

Reliance on Host Pipe 
Condition
Flow Diversion 
Requirements

Evaluation Parameters

CONSULTANT’S EVALUATION MATRIX

0

0

0

0

0

0

2

10

3

24

3

6

0

0

3

6

3

9

3

15

3

30

HDPE Sliplining

0

0

2

14

1

5

1

5

2

16

2

4

1

10

3

6

1

3

1

5

0

0

CIPP

3

21

3

21

3

15

2

10

0

0

0

0

3

30

3

6

1

3

2

10

2

20

Fiberglass Sliplining (Short Pipe)

2

14

3

21

2

10

2

10

0

0

0

0

2

20

1

2

1

3

3

15

1

10

$3,510,600
$1,404,800
$2,641,800
$1,909,800
$11,198,100
$4,228,100
$7,969,300
$5,641,600
$5,993,900
$3,212,400
$5,610,000
$3,897,300
$2,827,700
$1,196,200
$2,291,100
$1,605,400
$7,343,500
$6,899,100
$6,814,600
$4,478,800
$5,583,200
$4,169,300
$4,287,500
$3,023,700

0

0

96

3

30

137

1

10

118

2

20

103

0

0

112

3

30

158

1

10

110

2

20

100

0

0

105

3

30

113

1

10

108

2

20

108

0

0

100

3

30

120

1

10

118

2

20

115

0

0

100

3

30

89

1

10

137

2

20

115
100

0

0

3

30
10

146

2

20

125

.

.

.

.

98

1

.

.
PROCUREMENT METHODS EVALUATION
 DESIGN-BID-BUILD (DBB)
 PROGRESSIVE DESIGN BUILD
 CONSTRUCTION MANAGER AT RISK (CMR)
 DESIGN-BUILD (DB)


Traditional DB



Design-build-operate



Design-build-finance-operate



Design-build-own-operate-transfer

DESIGN‐BID‐BUILD
CMAR
PROGRESSIVE DB
DESIGN BUILD

DBO

DBOOT
DBFO

PROJECT DELIVERY SPECTRUM
PROCUREMENT METHODS EVALUATION
DESIGN-BID-BUILD (DBB)

 Separate contracts for design and construction.
OWNER

 Design documents are 100% complete
 Contractor selection is based entirely on cost.
DESIGNER

BUILDER

Contracts
Communication
PROCUREMENT METHODS EVALUATION
Select Design‐ Builder

PROGRESSIVE DESIGN BUILD
30%
Design

 Procurement process in a short timeframe
 Project can be implemented in phases

OWNER
VE

 Maximizes owner flexibility
 Initially cost for construction is not known

60%
Design
DB ENTITY 

 Cost is determined through combination of
negotiated and competitive processes

TRADE 
SUBS
Contracts
Communication

Constructability
Review
90%
Design
Constructability
Review
Submit/Approve
LS / GMP
PROCUREMENT METHODS EVALUATION
CONSTRUCTION MANAGER AT RISK (CMR)

 CMR handles some aspects of design
 Designer and CMR hold separate contracts with owner;

OWNER

CMR contracts directly with trades and takes on
“performance risk”
CMR

 Overlapping design and construction
 Professional management to an owner whose

TRADE 
SUBS

DESIGNER

organization may not have capabilities
 Facilitates phased construction
 Constructability and speed of implementation

Contracts
Communication
PROCUREMENT METHODS EVALUATION
TRADITIONAL DESIGN-BUILD (DB)

 Design and construction services in same contract.
 Single point of responsibility

OWNER

 Typically multi-step procurement process
 Owner transfer of responsibility; DB entity is liable

DB ENTITY 

for design and construction
 Overlapping design (~30%) and construction

DESIGNER

BUILDER

Contracts
Communication
BID PROCESS
D/CM/DB 
TEAM

CONSTRUCTION ENGINEERING (POST-DESIGN PHASE)
 Construction Administration

FINAL CONTRACT
DOCUMENTS

• Pre-Bid Documents
AGENCY 
PROGRAM 
MANAGER

 Review of Final Contract Documents.
 Project Advertisement and Bid Documents
Distribution
• Pre-Bid Conference.

RISK
MANAGEMENT

PROCUREMENT

ATTORNEY’S 
OFFICE

WRITTEN
COMMENTS

WRITTEN
COMMENTS

WRITTEN
COMMENTS

• Preparation and Issuance of Addenda
PROGRAM 
MANAGER

• Bid Opening and Award
• Preparation of As-Bid Contract Documents
 Construction Management

MEETINGS AS NECESSARY

D/CM/DB 
TEAM

FINAL BID
DOCUMENTS
Questions?

Thank you!
Credits:
Rod Lovett, MD‐WASD
Ricardo Vieira, LAN

Más contenido relacionado

Similar a Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-14-2011

In Rural Trenchless Apps
In Rural Trenchless AppsIn Rural Trenchless Apps
In Rural Trenchless Appsebiskis
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSARFARAZ24
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSARFARAZ24
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014San Diego County Water Authority
 
Inspecta OTD presentation
Inspecta OTD presentation Inspecta OTD presentation
Inspecta OTD presentation inacatrine
 
Abdullah Al Dossary - Length Maximization of Scrapable Pipeline Segment
Abdullah Al Dossary - Length Maximization of Scrapable Pipeline SegmentAbdullah Al Dossary - Length Maximization of Scrapable Pipeline Segment
Abdullah Al Dossary - Length Maximization of Scrapable Pipeline SegmentRamy Saboungui
 
RCSS General Slides Low Res
RCSS General Slides Low ResRCSS General Slides Low Res
RCSS General Slides Low Resstevefinnie
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONElliott Molnar
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfParmeshworVetwal1
 
Buried Flexible Pipelines AS2566
Buried Flexible Pipelines AS2566Buried Flexible Pipelines AS2566
Buried Flexible Pipelines AS2566blenrayaust
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxssuser0a41e6
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxMathewHany1
 
NACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEERNACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEERRAMA SAMY
 

Similar a Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-14-2011 (20)

In Rural Trenchless Apps
In Rural Trenchless AppsIn Rural Trenchless Apps
In Rural Trenchless Apps
 
W10 not every bore is boring - sciandra
W10 not every bore is boring - sciandraW10 not every bore is boring - sciandra
W10 not every bore is boring - sciandra
 
UCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesUCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologies
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-ppt
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-ppt
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
 
Challenges for EPD implementation
Challenges for EPD implementationChallenges for EPD implementation
Challenges for EPD implementation
 
Tandur_Poornima_CV
Tandur_Poornima_CVTandur_Poornima_CV
Tandur_Poornima_CV
 
Srp 2018 00
Srp 2018 00Srp 2018 00
Srp 2018 00
 
Inspecta OTD presentation
Inspecta OTD presentation Inspecta OTD presentation
Inspecta OTD presentation
 
Abdullah Al Dossary - Length Maximization of Scrapable Pipeline Segment
Abdullah Al Dossary - Length Maximization of Scrapable Pipeline SegmentAbdullah Al Dossary - Length Maximization of Scrapable Pipeline Segment
Abdullah Al Dossary - Length Maximization of Scrapable Pipeline Segment
 
CalAPA statewide technical webinar presentations
CalAPA statewide technical webinar presentationsCalAPA statewide technical webinar presentations
CalAPA statewide technical webinar presentations
 
RCSS General Slides Low Res
RCSS General Slides Low ResRCSS General Slides Low Res
RCSS General Slides Low Res
 
product_testing.ppt
product_testing.pptproduct_testing.ppt
product_testing.ppt
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
 
Buried Flexible Pipelines AS2566
Buried Flexible Pipelines AS2566Buried Flexible Pipelines AS2566
Buried Flexible Pipelines AS2566
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptx
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptx
 
NACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEERNACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEER
 

Más de ascemiami-dade

3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...ascemiami-dade
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvementsascemiami-dade
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectascemiami-dade
 
2.4 fll airport improvements
2.4 fll airport improvements2.4 fll airport improvements
2.4 fll airport improvementsascemiami-dade
 
K.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionK.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionascemiami-dade
 
3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...ascemiami-dade
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvementsascemiami-dade
 
3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...ascemiami-dade
 
3.2 wpb transit village
3.2 wpb transit village3.2 wpb transit village
3.2 wpb transit villageascemiami-dade
 
3.3 everglades restoration plans
3.3 everglades restoration plans3.3 everglades restoration plans
3.3 everglades restoration plansascemiami-dade
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal linkascemiami-dade
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal linkascemiami-dade
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel ceiascemiami-dade
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoirascemiami-dade
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoirascemiami-dade
 

Más de ascemiami-dade (20)

3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvements
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
2.4 fll airport improvements
2.4 fll airport improvements2.4 fll airport improvements
2.4 fll airport improvements
 
K.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionK.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progression
 
3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...3.1 defining level of service based on dynamic environmental, economic, and s...
3.1 defining level of service based on dynamic environmental, economic, and s...
 
2.3 i 595 improvements
2.3 i 595 improvements2.3 i 595 improvements
2.3 i 595 improvements
 
4 public policy panel
4   public policy panel4   public policy panel
4 public policy panel
 
3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...3.4 northern everglades payment for environmental services a public private p...
3.4 northern everglades payment for environmental services a public private p...
 
4 cards
4   cards4   cards
4 cards
 
3.2 wpb transit village
3.2 wpb transit village3.2 wpb transit village
3.2 wpb transit village
 
3.3 everglades restoration plans
3.3 everglades restoration plans3.3 everglades restoration plans
3.3 everglades restoration plans
 
3 climate change
3   climate change3   climate change
3 climate change
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal link
 
2.2 tri rail coastal link
2.2 tri rail coastal link2.2 tri rail coastal link
2.2 tri rail coastal link
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel cei
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir
 
2 transportation
2   transportation2   transportation
2 transportation
 
1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir1.4 l 8 feb and c51 reservoir
1.4 l 8 feb and c51 reservoir
 
1.3 pbcwud update
1.3 pbcwud update1.3 pbcwud update
1.3 pbcwud update
 

Último

Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 

Último (20)

Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 

Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-14-2011