What’s really new in
Simplified DBR?
                                                           TOCICO 2006 Conference




 Eli Schragenheim
 Amir Weisenstern
 Amir Schragenheim

                     © 2006 TOCICO. All rights reserved.                        1
The good old DBR
                                                            TOCICO 2006 Conference




• DBR was developed in the mid 80s as a relatively
  simple, yet effective, production planning
  methodology.
• DBR centers on detailed finite capacity scheduling
  of the capacity resource constraint (CCR).
• DBR was developed under the assumption of
  getting orders from the sales, without truly
  impacting the committed dates, and coming up with
  the best planning possible under the
  circumstances.
                                      2
                      © 2006 TOCICO. All rights reserved.
The main benefits of scheduling the CCR
     that we do not want to lose
                                                               TOCICO 2006 Conference


1. Being able to tie the Rope so that the CCR will
   not starve and will not waste its capacity
   •   Exploiting the CCR capacity

2. Being able to know whether the delivery dates,
   which we get from Sales, are safe
   •   Proper subordination to the market

3. Smooth the load on the whole shop to prevent
   from too large temporary peaks of load
   •   Enabling the full subordination of the non-constraints

                                         3
                         © 2006 TOCICO. All rights reserved.
Finite capacity scheduling of the CCR
         Is the focus absolutely right?
                                                               TOCICO 2006 Conference


• The focus of Operations is on the exploitation of
  the capacity of the CCR
   − Many times it leads to problematic subordination to the
     market
      − Orders that have relatively low T/CU are pushed
        forward in time
      − The identity of the client and the impact on the
        reputation are not always taken into consideration
      − There is a huge difficulty to deal with urgent orders
      − A policy of “adherence to the CCR schedule” makes it
        difficult to enter changes caused by customers who
        have new priorities
   − The result is that the response to the market
     demand lacks flexibility
                                         4
                         © 2006 TOCICO. All rights reserved.
Finite capacity scheduling of the CCR
         Is it right for make-to-stock?
                                                                TOCICO 2006 Conference



• The need for better flexibility is especially noted in
  orders that are made to stock
    − Because the true priority of a stock order is not known
      at the time of the scheduling
       − The priority of stock orders depends on the finished
         goods stock versus the demand. This could change in a
         day
• The current practice is to assign a date to the stock
  order and then base the CCR schedule on that date,
  like any make-to-order
    − The date is based on forecast
    − Many times the derived priorities of the schedule are
      wrong                               5
                          © 2006 TOCICO. All rights reserved.
Finite capacity scheduling of the CCR
          Three buffers to maintain
                                                               TOCICO 2006 Conference




• The CCR detailed schedule forces three different
  buffers to be implemented, without good priority
  mechanism between them
   − The Shipping Buffer protects the due-dates
   − The CCR Buffer protects the detailed schedule
   − The Assembly Buffer – controls the material release of
     non-CCR parts
     − What does it really protect? Isn’t it just an extension of
       the shipping buffer?

                                         6
                         © 2006 TOCICO. All rights reserved.
Finite capacity scheduling of the CCR
               not always simple
                                                                TOCICO 2006 Conference



• In certain cases the finite capacity scheduling of the
  CCR is especially complex
    − Depended setups and other technical limitations that
      forbid certain sequences
    − Time-per-batch operations, like ovens, that work on
      several orders together provided certain conditions
      apply to all orders
    − Many machines, which are NOT identical, are the CCR
    − CCR operations that feed other CCR operations
• Very few, if at all, existing DBR program can handle
  those complexities
                                          7
                          © 2006 TOCICO. All rights reserved.
When one is used to focus on the one CCR
                                                                  TOCICO 2006 Conference



• When the market fluctuates, even a real CCR should
  have periods of low load
   − Thus, at those times the constraint is just the market
   − Should we still focus on the CCR also at those times?
• Sometimes the CCR shifts from one resource to
  another
   − It could be because Sales took T/CU too seriously
   − The equilibrium is jeopardized – all the subordination
     processes change
   − A lot of data has to be checked, maintained and fed into the
     DBR software
      − Note especially that all the buffers change!
                                            8
                            © 2006 TOCICO. All rights reserved.
Current practice of coping
          with the negatives
                                                              TOCICO 2006 Conference




• Frequent re-scheduling
   − Thus considering the most updated information
   − Alas, new problems rise from re-scheduling
     − A local change causes a significant change all over:
     − Dates promised are not safe
     − Frequent changes to the material release schedule
       could cause chaos and inferior confidence in the
       planning
     − A lot of reporting needs to be done accurately between
       re-scheduling
                                        9
                        © 2006 TOCICO. All rights reserved.
Some Key Observations
                                                                TOCICO 2006 Conference



• The market demand is a major constraint even
  when a capacity constraint resource is active
   − Failing to subordinate to the market could lead to a
     significant dive down of the market demand
   − Elevating the internal constraint won’t improve anything
     unless the market demand is elevated as well

• In such a case how do we exploit both constraints?
   − Not disappointing the market
   − Not losing too much precious capacity of the CCR


                                         10
                          © 2006 TOCICO. All rights reserved.
The initial direction of the solution:
                the basic SDBR                                 TOCICO 2006 Conference



•   As the market is the major constraint, let’s protect
    the market with just the shipping buffer
    − All materials are released based on due-date minus
      the shipping buffer
    − The sequence at the CCR is not planned

•   The less detailed is the planning the more critical
    is the quality of the decisions taken at the
    execution
•   The role of the execution control is now critical:
    dictating the right priorities on the floor
                                        11
                         © 2006 TOCICO. All rights reserved.
The initial direction of the solution:
   More focus on buffer management
                                                                 TOCICO 2006 Conference



• Generally speaking every single order is given enough time
  to flow through the shop floor
• The Rope ensures that only orders to be delivered within
  the shipping buffer time are released to the floor
• At each work center, including the CCR, the sensible
  decision which order to do next depends on the state of the
  buffers of the relevant orders
• Definition: the buffer status of the order is the percentage of
  the buffer consumed
• The higher the buffer status is the higher the priority of the
  order
                                          12
                           © 2006 TOCICO. All rights reserved.
The benefits of the SDBR direction
                                                           TOCICO 2006 Conference




• Simpler to implement
• Having just one buffer makes the priority list clear
  at all times
• Maintaining much more flexibility to meet the
  changing requirements of the clients
• Signals clearly that the major constraint is the
  market demand, thus even the CCR should
  subordinate to it


                                    13
                     © 2006 TOCICO. All rights reserved.
Concerns / negative branches of
               SDBR
                                                              TOCICO 2006 Conference



1. Failing to exploit the capacity of the CCR
2. Overloading the CCR, thus causing disruption
   of the due-date performance
3. Maintaining too large buffers, causing some
   materials to be released too soon
   •   This is the least concerning NBR and we won’t
       discuss it
               Do we agree so far?
       Are the above your main concerns?

                                       14
                        © 2006 TOCICO. All rights reserved.
A common basic conflict to consider
                                                                        TOCICO 2006 Conference



                    B                                              D
                         Ensure smooth
                                                                       Implement a very
                         execution and
                                                                       simple solution
                        implementation
A
Have a successful   By how much the results
                    would be compromised
working solution    using the simple
                                                                          Conflict
    in place        solution?

                    C                                              D’
                                                                        Implement a
                     Draw the best results
                                                                        sophisticated
                      out of the solution
                                                                          solution



                                            15
                             © 2006 TOCICO. All rights reserved.
Failing to exploit the CCR capacity
                                                                    TOCICO 2006 Conference

•     Three types of miss-exploitation of the CCR
      1. Starvation, meaning there is enough planned work for the
         CCR to do, but none of it is ready at the CCR at this time
      2. The sequence at which the work arrives to the CCR forces
         waste of capacity of the CCR
      3. The CCR works on things that are not truly needed
•     The third type is controlled by the master production
      schedule, not by the CCR schedule
•     The second type is relevant only when dependent
      setups have a major impact
      − In that case we need to come back to DBR, with some
        changes
    Let’s concentrate on how to prevent starvation in SDBR
                                             16
                              © 2006 TOCICO. All rights reserved.
Preventing starvation in SDBR
                                                                    TOCICO 2006 Conference


• When the market demand is recognized as the major
  constraint, we expect that even the CCR be able to
  subordinate to the market
    − Ensure excellent due-date performance, even when Murphy
      hits the CCR itself
    − Be able to respond within the tolerance of the market
    − All the above make it necessary to maintain some protected
      capacity of the CCR itself
    − Hence, some very limited starvation does not impact the profit
• The shipping buffer is usually long enough to provide enough
  WIP at the weakest link (the CCR)
    − Assuming the RoadRunner ethics is in place
• The work at the CCR should be monitored daily
                                             17
                              © 2006 TOCICO. All rights reserved.
Facing the second concern:
            overloading the CCR
                                                                TOCICO 2006 Conference


• Definition: Planned load is the accumulation of
  the derived load on the CCR (the weakest
  link) of all the firm orders that have to be
  delivered within a certain horizon of time
• The planned load is a number of hours/days
   − it is NOT a description of the spread of the load over
     time
   − Suppose we have only three orders in the backlog,
     estimated CCR time are: 50, 125 and 55 hours
     − The planned load is 230 hours
     − The sequence is not determined
                                         18
                          © 2006 TOCICO. All rights reserved.
What does the planned load tell us?
                                                               TOCICO 2006 Conference


• The planned load is a rough estimation of the time
  when the specific resource would be able to
  work on a new order
   − Assuming the resource is able to work all the time
     without starvation
   − Assuming the new order has no special priority relative
     to the other orders

• When we monitor the planned load of the CCR we
  get a pretty good idea of the lead time
   − The planned load plus enough safety for the
     downstream operations
                                        19
                         © 2006 TOCICO. All rights reserved.
An example: what do we know on the
       environment just from what we see?
                                                                  TOCICO 2006 Conference




• The red bar shows the planned load of 192 hours of CCR work
• The green bar shows the orders already reside at the CCR site
   • This information is harder to get
• We can easily assume the minimum safe lead time for a new
order is around 240 working hours from now
   • Assuming 40 plus hours are more than enough from the CCR to
   completion
   • Assuming the new order could easily reach the CCR in 192 hours
                                           20
                            © 2006 TOCICO. All rights reserved.
The difference between a finite-capacity
      schedule and the planned load
                                                                    TOCICO 2006 Conference



• On the face of it the planned load is a schedule
    − It is similar to “forward loading” process
    − But, there is no sophistication in the sequence of orders
    − No efforts are done to validate the material would really arrive to
      the CCR on the time predicted by the planned load
    − The planned load should not be treated as a schedule – it
      should not dictate any sequence the operator has to follow

• The most important asset of the planned load is the
  rough determination of the time a new order has to
  wait for the CCR

                                             21
                              © 2006 TOCICO. All rights reserved.
Dealing with the overloading concern
                                                                TOCICO 2006 Conference


• The planned load of the CCR, at any given time,
  should be compared to the standard lead time
  required by the market
   − Certainly we expect the planned load to be LESS than
     the standard lead-time
• There is, yet, no guaranty that the load on the CCR
  would be smooth
   − A cluster of orders to be shipped at the same date could
     be problematic
• We need to take another step and control the
  promised dates of deliveries according to the
  CCR’s planned load
                                         22
                          © 2006 TOCICO. All rights reserved.
Promising delivery dates based on
          the planned load
                                                                TOCICO 2006 Conference



• In order to achieve reliable delivery dates Sales
  and Operations must synchronize their actions
• Instead of Sales promising delivery dates and then
  Operations trying to meet as many of the dates as
  possible, let’s build a mechanism to determine
  the dates that Operation can commit to deliver
• As the planned load is a rough estimation of the
  time a new order would be processed by the CCR,
  we should add a time buffer to the planned load and
  get a “safe delivery date” for the order
   − Let’s decide to add ½ of the total shipping buffer
                                         23
                          © 2006 TOCICO. All rights reserved.
This is how it looks like
                                                                       TOCICO 2006 Conference




        All the required CCR load for the orders
        that have a committed delivery date have
        been accumulated here

Daily                                      50% of buffer                   We can
Load                                                                       safely
                                                                           deliver here

                                                        The planned load



                          Time (days)



                                            24
                             © 2006 TOCICO. All rights reserved.
And this is how we tie the Rope
             to the Planned Load
                                                                       TOCICO 2006 Conference




                       50% of buffer             50% of buffer
Daily                                                                          We can
Load                                                                            safely
                                                                             deliver here
                                full buffer
             Release
              point

                              Time (days)
The same approach, assuming the new order would be processed
roughly at the current planned load time, leads us also to release the
raw materials at half of the total shipping buffer before that time.
All in all we have a full buffer between the release and delivery
                                                25
                                 © 2006 TOCICO. All rights reserved.
The dilemma of quoting short lead-times
                                                             TOCICO 2006 Conference

• When the planned load is close to the standard
  lead-time or longer, then we know we must quote
  the safe date
• But, what happens when the safe-date is much
  shorter than the standard quoted lead-time?
    Should we quote short quoted lead times
              whenever possible?
• On one hand we could attract more clients now
• On the other hand, the clients would expect those
  short deliveries as the regular service also in the
  future and for the same price
                                      26
                       © 2006 TOCICO. All rights reserved.
The dilemma of quoting short lead-times
                                                                TOCICO 2006 Conference



• The solution is offering a service of very fast
  deliveries for a considerable markup, while keeping
  the regular prices for standard time, but fully
  reliable, deliveries
• Then we have to deal with orders with very short
  lead-time, while the regular orders have much
  longer lead-times
   − We’ll handle the negative ramifications, already
     mentioned earlier, later in the presentation



                                         27
                          © 2006 TOCICO. All rights reserved.
The shipping buffer when the safe date is earlier
            than the quoted lead time
                                                                                  TOCICO 2006 Conference




Daily                                              Safe
Load                                               delivery              Addition to
                     full buffer                                         the buffer               We
                                                                                                promise
                                                                                               standard
          release                                                                              lead time
           point
                                   Standard
                                   lead time


                         Time (days)

The actual shipping buffer for this order is expanded from the
release date, dictated by the planned load minus half of the
original buffer, until the formal date for the regular price
                                                  28
                                   © 2006 TOCICO. All rights reserved.
Points of discussion so far
                                                                TOCICO 2006 Conference


• Assuming dependent setups are not significant,
  what are the negative branches of using SDBR in
  general?
   − Would DBR work better? At what situations?
   − Do we need more injections to make SDBR (one buffer
     planning) work properly?
• How should we treat quoting times that are later
  than the internal safe-date?
   − Should we keep the shipping buffer fixed and release
     the materials accordingly?
      − We thus force idle time on the weakest link. What are the
        possible ramifications?
                                         29
                          © 2006 TOCICO. All rights reserved.
The complication of depended setups
                                                                  TOCICO 2006 Conference

• Depended setups means significant dependency of the
setup time on the previous product processed at the
specific resource
• The first question to raise: if the machine would process
according to an arbitrary sequence, would it become a
true bottleneck?
   − If the answer is NO, then there is no problem whatsoever to
     implement SDBR/BM without distortion
   − Many times it is worthwhile to invest in adding capacity, or
     coming up with engineering innovation, to get rid of the
     negative impact of dependent setups
   − Otherwise we have you yield to a preferred sequence
     imposed by the dependent setups

                                           30
                            © 2006 TOCICO. All rights reserved.
Regarding dependent setups
                                                               TOCICO 2006 Conference


•   It could be the case that the preferred sequence
    is dictated by another resource – not the CCR
•   A preferred sequence is not necessarily a well-
    defined unique sequence, but a general
    sequence between families of items that within
    the family the setup is relatively short
•   The assumption is that violating the sequence
    would turn the resource into a bottleneck
    − Certainly we need to consider a situation where few
      violations of the sequence would not create a
      bottleneck
                                        31
                         © 2006 TOCICO. All rights reserved.
Dealing with dependent setups:
         two main approaches
                                                               TOCICO 2006 Conference


•   In a situation where we cannot afford an arbitrary
    sequence on the CCR, like in dependent setups,
    two optional approaches should be checked
    1. The shipping buffer is long enough to provide
       enough choice for the foreman, considering the
       priorities of the orders
      − In this case SDBR is still the preferable method
    2. A fixed sequence determined for the CCR ahead of
       time, which is protected by a CCR buffer
      − Note that what is critical point is the sequence, NOT
        the exact quantity to be produced!
                                        32
                         © 2006 TOCICO. All rights reserved.
Dealing with more than one
           standard lead time
                                                                TOCICO 2006 Conference


•   Defining the problem:
When a company has different commitments to
  lead times, then promising reliable due-dates
  is problematic because not all the orders are
                known at the time
•   This problem includes different categories:
    1. The Rapid Response viable vision template
    2. Commitment to a strategic client to fast response
    3. Maintaining product mix with highly variable standard
       lead times in the industry
    4. Items that are make to stock
                                         33
                          © 2006 TOCICO. All rights reserved.
Reserving capacity for the faster items
                                                                                TOCICO 2006 Conference




                                                                              Only this portion is
                                                                             free for allocation to
                                                                                normal orders


                                           Reserved



          Super fast       Fast                                         Standard lead
                                                                            time

The proposed approach is to dedicate certain percentage of the
capacity for the faster response items.
The calculation of the planned load for determining the safe dates is
now based on (100 – ReservedPercentage) of the available capacity
                                                 34
                                  © 2006 TOCICO. All rights reserved.
Managing the reserved capacity
                                                               TOCICO 2006 Conference



• How much reserved capacity we need?
  − Like in the determination of buffer size a good initial
    guess is all we can hope for
  − Then, we need to look for a way to assess whether the
    current reservation level is about right




                                        35
                         © 2006 TOCICO. All rights reserved.
What do we lose from determining a
        too high reservation level?
                                                                 TOCICO 2006 Conference



• Do we lose precious CCR capacity when we have
  reserved too much capacity for the “special” items?
   − We do not really mean that every day the CCR will work
     X% on the special orders and (100-x)% on regular orders
      − The CCR should work on whatever is available, taking into
        account the buffer statuses
   − Thus, when there is not much work for the special
     orders, then most regular orders would be processed
     earlier than predicted
      − We are not going to move the due-dates backwards in time
      − But, it is easy to move the release of materials backwards
        when it is evident the CCR would be able to process them
        earlier
                                          36
                           © 2006 TOCICO. All rights reserved.
What do we lose from determining a too
        high reservation level?
                                                            TOCICO 2006 Conference




• When we plan with high reservation of capacity the
  safe-dates are too conservative
• So, when the safe-dates lie beyond the standard
  lead-time, we might lose market demand
• Then we lose something substantial, which makes
  it worth to re-check the amount of reservation




                                     37
                      © 2006 TOCICO. All rights reserved.
What happens when the reservation level
              is too low?
                                                                TOCICO 2006 Conference



• The high number of special orders would push the
  completion of regular orders later in time
   − As long as the calculated safe dates for regular orders
     are far from the standard lead times the situation is
     under control
   − When the buffers of the regular order are not extended,
     then more regular orders are pushed into the red, and
     the number of red orders rises sharply
   − Then there is a need to increase the reservation level,
     causing the safe dates to be later in time, possibly
     causing losing some sales

                                         38
                          © 2006 TOCICO. All rights reserved.
Tools for managing the reservation level
                                                                TOCICO 2006 Conference



• Monitoring the two parts of the planned load
   − The first part is the regular planned load, consisting of
     all the regular commitments, and how the front of the
     planned load stands relative to the standard lead time
   − The second part contains the special orders assuming
     only the reserved capacity is available for them and
     how close they are to the short lead-times references




                                         39
                          © 2006 TOCICO. All rights reserved.
Tools for managing the reservation level
                                                              TOCICO 2006 Conference



• Eventually we need to control the overall capacity
  and how it is used for both regular and special
  orders
• For that we need full planned load for the
  shortest lead-time (like super-fast)
   − All the orders that need to be worked on within the
     short lead time
   − The planned load needs to show some excess
     capacity within the short time frame


                                       40
                        © 2006 TOCICO. All rights reserved.
Main Discussion
                                                                    TOCICO 2006 Conference


• The planned load as a major planning tool (dictating due-
  dates)
    − Effectiveness and how accurate it has to be?
    − Ways of calculating the planned load (with or without setups and
      maintenance)
    − After how many resources we need to monitor their planned load?
• The planned load as support to execution decisions
  (temporary increase of buffer)
    − How does the planned load interact with buffer management?
• When the safe-date is much earlier than standard – why
  extending the buffers? If so, why not extend just the green?
• Other questions / reservations
                                             41
                              © 2006 TOCICO. All rights reserved.

Más contenido relacionado

Destacado

B2B Growth Hacking: How to build a Growth Engine in B2B
B2B Growth Hacking: How to build a Growth Engine in B2BB2B Growth Hacking: How to build a Growth Engine in B2B
B2B Growth Hacking: How to build a Growth Engine in B2BVladimir Blagojevic
 
Webinar Planificación Estratégica usando el Thinking Process (TOC)
Webinar Planificación Estratégica usando el Thinking Process (TOC)Webinar Planificación Estratégica usando el Thinking Process (TOC)
Webinar Planificación Estratégica usando el Thinking Process (TOC)Qualiplus
 
Trabajo en equipo y toc
Trabajo en equipo y tocTrabajo en equipo y toc
Trabajo en equipo y tocJesus Garcia
 
TOC for Education
TOC for EducationTOC for Education
TOC for Educationmcmoonitz
 
Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...
Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...
Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...Héctor Debernardo
 
The 3 Layers of Logic
The 3 Layers of LogicThe 3 Layers of Logic
The 3 Layers of LogicHumbertoRB
 
Conflict resolution diagram tutorial
Conflict resolution diagram tutorialConflict resolution diagram tutorial
Conflict resolution diagram tutorialAgileCoach.net
 
Book Summary of Contagious: Why Things Catch On by Jonah Berger
Book Summary of Contagious: Why Things Catch On by Jonah BergerBook Summary of Contagious: Why Things Catch On by Jonah Berger
Book Summary of Contagious: Why Things Catch On by Jonah BergerAmir Mohammad Redzuan
 
Aplicabilidad de la teoria de restricciones en las empresas
Aplicabilidad de la teoria de restricciones  en las empresasAplicabilidad de la teoria de restricciones  en las empresas
Aplicabilidad de la teoria de restricciones en las empresasWilmar Franco
 
Cómo gamificar un curso (Taller en MoodleMoot Colombia 2014)
Cómo gamificar un curso  (Taller en MoodleMoot Colombia 2014)Cómo gamificar un curso  (Taller en MoodleMoot Colombia 2014)
Cómo gamificar un curso (Taller en MoodleMoot Colombia 2014)Fernando Santamaría
 
How to Overcome Your Fear of Failure
How to Overcome Your Fear of FailureHow to Overcome Your Fear of Failure
How to Overcome Your Fear of FailureFaisal Hoque
 

Destacado (16)

B2B Growth Hacking: How to build a Growth Engine in B2B
B2B Growth Hacking: How to build a Growth Engine in B2BB2B Growth Hacking: How to build a Growth Engine in B2B
B2B Growth Hacking: How to build a Growth Engine in B2B
 
Autodesarrollo del liderazgo
Autodesarrollo del liderazgoAutodesarrollo del liderazgo
Autodesarrollo del liderazgo
 
Webinar Planificación Estratégica usando el Thinking Process (TOC)
Webinar Planificación Estratégica usando el Thinking Process (TOC)Webinar Planificación Estratégica usando el Thinking Process (TOC)
Webinar Planificación Estratégica usando el Thinking Process (TOC)
 
Trabajo en equipo y toc
Trabajo en equipo y tocTrabajo en equipo y toc
Trabajo en equipo y toc
 
Social Entrepreneurship
Social Entrepreneurship Social Entrepreneurship
Social Entrepreneurship
 
TOC for Education
TOC for EducationTOC for Education
TOC for Education
 
Capacitacion Empresarial TOC
Capacitacion Empresarial TOCCapacitacion Empresarial TOC
Capacitacion Empresarial TOC
 
Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...
Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...
Versión reducida de "Luz, cámara... TOC!. Una manera entretenida de aprender ...
 
Team Trust Canvas eng
Team Trust Canvas   engTeam Trust Canvas   eng
Team Trust Canvas eng
 
The 3 Layers of Logic
The 3 Layers of LogicThe 3 Layers of Logic
The 3 Layers of Logic
 
Conflict resolution diagram tutorial
Conflict resolution diagram tutorialConflict resolution diagram tutorial
Conflict resolution diagram tutorial
 
Book Summary of Contagious: Why Things Catch On by Jonah Berger
Book Summary of Contagious: Why Things Catch On by Jonah BergerBook Summary of Contagious: Why Things Catch On by Jonah Berger
Book Summary of Contagious: Why Things Catch On by Jonah Berger
 
Aplicabilidad de la teoria de restricciones en las empresas
Aplicabilidad de la teoria de restricciones  en las empresasAplicabilidad de la teoria de restricciones  en las empresas
Aplicabilidad de la teoria de restricciones en las empresas
 
Cómo gamificar un curso (Taller en MoodleMoot Colombia 2014)
Cómo gamificar un curso  (Taller en MoodleMoot Colombia 2014)Cómo gamificar un curso  (Taller en MoodleMoot Colombia 2014)
Cómo gamificar un curso (Taller en MoodleMoot Colombia 2014)
 
How to Overcome Your Fear of Failure
How to Overcome Your Fear of FailureHow to Overcome Your Fear of Failure
How to Overcome Your Fear of Failure
 
The State of My Industry
The State of My IndustryThe State of My Industry
The State of My Industry
 

Similar a Whats Really New In Simplified Dbr Schragenheim Weisenstern

“Achieving Mine to Market Throughput” – Iluka South West Operations – Case...
“Achieving Mine to Market Throughput”   – Iluka South West Operations –  Case...“Achieving Mine to Market Throughput”   – Iluka South West Operations –  Case...
“Achieving Mine to Market Throughput” – Iluka South West Operations – Case...Robert Bolton
 
Supply chain logistic review by lisa ferguson
Supply chain logistic review by lisa fergusonSupply chain logistic review by lisa ferguson
Supply chain logistic review by lisa fergusonUtkan Uluçay, MSc., CDDP
 
Retail toc get your hands dirty in the implementation - humberto baptista v1.0
Retail toc   get your hands dirty in the implementation - humberto baptista v1.0Retail toc   get your hands dirty in the implementation - humberto baptista v1.0
Retail toc get your hands dirty in the implementation - humberto baptista v1.0HumbertoRB
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydNitin Sethi
 
Boeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceBoeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceNandhagopal Muralithar
 
Innovation as a Necessity in the UK Water Sector
Innovation as a Necessity in the UK Water SectorInnovation as a Necessity in the UK Water Sector
Innovation as a Necessity in the UK Water SectorJames Dunning
 
Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...
Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...
Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...HostedbyConfluent
 
Lubricants and Greases Manufacturing Plants
Lubricants and Greases Manufacturing PlantsLubricants and Greases Manufacturing Plants
Lubricants and Greases Manufacturing PlantsEko Kiswanto
 
Week 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptx
Week 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptxWeek 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptx
Week 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptxAznain Dogar
 
Synchronized manufacturing training
Synchronized manufacturing trainingSynchronized manufacturing training
Synchronized manufacturing trainingTonyEMadison
 
Synchronized Manufacturing Training
Synchronized Manufacturing TrainingSynchronized Manufacturing Training
Synchronized Manufacturing TrainingTonyEMadison
 
Commodity profile strategy
Commodity profile strategyCommodity profile strategy
Commodity profile strategyRachmat Abubakar
 
Bpcl final implementation -uVs
Bpcl final implementation -uVsBpcl final implementation -uVs
Bpcl final implementation -uVsUtkarsh Vashistha
 
Supply chain management
Supply chain management Supply chain management
Supply chain management ARif Khan
 

Similar a Whats Really New In Simplified Dbr Schragenheim Weisenstern (20)

“Achieving Mine to Market Throughput” – Iluka South West Operations – Case...
“Achieving Mine to Market Throughput”   – Iluka South West Operations –  Case...“Achieving Mine to Market Throughput”   – Iluka South West Operations –  Case...
“Achieving Mine to Market Throughput” – Iluka South West Operations – Case...
 
Supply chain logistic review by lisa ferguson
Supply chain logistic review by lisa fergusonSupply chain logistic review by lisa ferguson
Supply chain logistic review by lisa ferguson
 
Newparadigmdigitaloilfield
NewparadigmdigitaloilfieldNewparadigmdigitaloilfield
Newparadigmdigitaloilfield
 
Retail toc get your hands dirty in the implementation - humberto baptista v1.0
Retail toc   get your hands dirty in the implementation - humberto baptista v1.0Retail toc   get your hands dirty in the implementation - humberto baptista v1.0
Retail toc get your hands dirty in the implementation - humberto baptista v1.0
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
Book Review-Toyota Production System
Book Review-Toyota Production SystemBook Review-Toyota Production System
Book Review-Toyota Production System
 
Dermarkar
DermarkarDermarkar
Dermarkar
 
Boeing - Reliability Centered Maintenance
Boeing - Reliability Centered MaintenanceBoeing - Reliability Centered Maintenance
Boeing - Reliability Centered Maintenance
 
Using sdbr in rapid response project
Using sdbr in rapid response projectUsing sdbr in rapid response project
Using sdbr in rapid response project
 
Decc investor simulation workshop intro presentation_v 1
Decc investor simulation workshop intro presentation_v 1Decc investor simulation workshop intro presentation_v 1
Decc investor simulation workshop intro presentation_v 1
 
Innovation as a Necessity in the UK Water Sector
Innovation as a Necessity in the UK Water SectorInnovation as a Necessity in the UK Water Sector
Innovation as a Necessity in the UK Water Sector
 
Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...
Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...
Enabling product personalisation using Apache Kafka, Apache Pinot and Trino w...
 
Lubricants and Greases Manufacturing Plants
Lubricants and Greases Manufacturing PlantsLubricants and Greases Manufacturing Plants
Lubricants and Greases Manufacturing Plants
 
Week 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptx
Week 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptxWeek 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptx
Week 3 & 4 DND (NETWORK DESIGN IN THE SUPPLY CHAIN).pptx
 
Synchronized manufacturing training
Synchronized manufacturing trainingSynchronized manufacturing training
Synchronized manufacturing training
 
Synchronized Manufacturing Training
Synchronized Manufacturing TrainingSynchronized Manufacturing Training
Synchronized Manufacturing Training
 
Commodity profile strategy
Commodity profile strategyCommodity profile strategy
Commodity profile strategy
 
CS Offshore Project
CS Offshore ProjectCS Offshore Project
CS Offshore Project
 
Bpcl final implementation -uVs
Bpcl final implementation -uVsBpcl final implementation -uVs
Bpcl final implementation -uVs
 
Supply chain management
Supply chain management Supply chain management
Supply chain management
 

Más de Advance Operations Management School srl

Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...
Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...
Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...Advance Operations Management School srl
 
Webinar operational excellence 28 july last - Case study Samsonite - Advance ...
Webinar operational excellence 28 july last - Case study Samsonite - Advance ...Webinar operational excellence 28 july last - Case study Samsonite - Advance ...
Webinar operational excellence 28 july last - Case study Samsonite - Advance ...Advance Operations Management School srl
 
Lean Six Sigma: Best Practice per gestire la performance - Manager a confronto
Lean Six Sigma: Best Practice per gestire la performance - Manager a confrontoLean Six Sigma: Best Practice per gestire la performance - Manager a confronto
Lean Six Sigma: Best Practice per gestire la performance - Manager a confrontoAdvance Operations Management School srl
 
Automated Receiving System - A. Caradonna - J&J - Workshop Supply Chain Unin...
Automated Receiving System  - A. Caradonna - J&J - Workshop Supply Chain Unin...Automated Receiving System  - A. Caradonna - J&J - Workshop Supply Chain Unin...
Automated Receiving System - A. Caradonna - J&J - Workshop Supply Chain Unin...Advance Operations Management School srl
 
ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...
ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...
ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...Advance Operations Management School srl
 

Más de Advance Operations Management School srl (20)

Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...
Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...
Applicare concretamente la metodologia Lean per ridurre le scorte senza impat...
 
Webinar operational excellence 28 july last - Case study Samsonite - Advance ...
Webinar operational excellence 28 july last - Case study Samsonite - Advance ...Webinar operational excellence 28 july last - Case study Samsonite - Advance ...
Webinar operational excellence 28 july last - Case study Samsonite - Advance ...
 
Leadership nell'industria - Live Webinar Advance School
Leadership nell'industria - Live Webinar Advance SchoolLeadership nell'industria - Live Webinar Advance School
Leadership nell'industria - Live Webinar Advance School
 
Six Sigma Eliminare la difettosità e garantire il time to market
Six Sigma Eliminare la difettosità e garantire il time to marketSix Sigma Eliminare la difettosità e garantire il time to market
Six Sigma Eliminare la difettosità e garantire il time to market
 
Demand Driven MRP - Come implementarlo con successo in azienda
Demand Driven MRP -  Come implementarlo con successo in aziendaDemand Driven MRP -  Come implementarlo con successo in azienda
Demand Driven MRP - Come implementarlo con successo in azienda
 
Top Workshop - Come impostare i parametri MRP/MPS su SAP
Top Workshop - Come impostare i parametri MRP/MPS su SAPTop Workshop - Come impostare i parametri MRP/MPS su SAP
Top Workshop - Come impostare i parametri MRP/MPS su SAP
 
Lean Six Sigma: Best Practice per gestire la performance - Manager a confronto
Lean Six Sigma: Best Practice per gestire la performance - Manager a confrontoLean Six Sigma: Best Practice per gestire la performance - Manager a confronto
Lean Six Sigma: Best Practice per gestire la performance - Manager a confronto
 
Mettere i fornitori al centro dell'azienda
Mettere i fornitori al centro dell'aziendaMettere i fornitori al centro dell'azienda
Mettere i fornitori al centro dell'azienda
 
BIQ, Built in Quality- verso la Lean Transformation - CAT
BIQ, Built in Quality- verso la Lean Transformation - CATBIQ, Built in Quality- verso la Lean Transformation - CAT
BIQ, Built in Quality- verso la Lean Transformation - CAT
 
Articolo lean manufacturing in Italia
Articolo lean manufacturing in ItaliaArticolo lean manufacturing in Italia
Articolo lean manufacturing in Italia
 
Western LEAN -Evolution
Western LEAN -EvolutionWestern LEAN -Evolution
Western LEAN -Evolution
 
Automated Receiving System - A. Caradonna - J&J - Workshop Supply Chain Unin...
Automated Receiving System  - A. Caradonna - J&J - Workshop Supply Chain Unin...Automated Receiving System  - A. Caradonna - J&J - Workshop Supply Chain Unin...
Automated Receiving System - A. Caradonna - J&J - Workshop Supply Chain Unin...
 
Space hunters 14 07 15 Pfizer - Workshop Unindustria AD-net
Space hunters 14 07 15 Pfizer - Workshop Unindustria AD-netSpace hunters 14 07 15 Pfizer - Workshop Unindustria AD-net
Space hunters 14 07 15 Pfizer - Workshop Unindustria AD-net
 
ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...
ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...
ll vantaggio competitivo derivante dall’inserimento di nuovi fornitori estern...
 
CIRCOR S&OP with Suppliers_ 19 feb_2015
CIRCOR S&OP with Suppliers_ 19 feb_2015CIRCOR S&OP with Suppliers_ 19 feb_2015
CIRCOR S&OP with Suppliers_ 19 feb_2015
 
ST- Turning supply chain disruptions into a competitive advantage
ST- Turning supply chain disruptions into a competitive advantageST- Turning supply chain disruptions into a competitive advantage
ST- Turning supply chain disruptions into a competitive advantage
 
Presentation_TOC_2_december_Vettor_CUOA
Presentation_TOC_2_december_Vettor_CUOAPresentation_TOC_2_december_Vettor_CUOA
Presentation_TOC_2_december_Vettor_CUOA
 
Lean a commessa_a_gatto_ottobre_2014
Lean a commessa_a_gatto_ottobre_2014Lean a commessa_a_gatto_ottobre_2014
Lean a commessa_a_gatto_ottobre_2014
 
Articolo daloiso informatizzazione_magazzino_set_2014
Articolo daloiso informatizzazione_magazzino_set_2014Articolo daloiso informatizzazione_magazzino_set_2014
Articolo daloiso informatizzazione_magazzino_set_2014
 
Articolo Mari rating-fornitori_ad-net_giugno_2014
Articolo Mari rating-fornitori_ad-net_giugno_2014Articolo Mari rating-fornitori_ad-net_giugno_2014
Articolo Mari rating-fornitori_ad-net_giugno_2014
 

Whats Really New In Simplified Dbr Schragenheim Weisenstern

  • 1. What’s really new in Simplified DBR? TOCICO 2006 Conference Eli Schragenheim Amir Weisenstern Amir Schragenheim © 2006 TOCICO. All rights reserved. 1
  • 2. The good old DBR TOCICO 2006 Conference • DBR was developed in the mid 80s as a relatively simple, yet effective, production planning methodology. • DBR centers on detailed finite capacity scheduling of the capacity resource constraint (CCR). • DBR was developed under the assumption of getting orders from the sales, without truly impacting the committed dates, and coming up with the best planning possible under the circumstances. 2 © 2006 TOCICO. All rights reserved.
  • 3. The main benefits of scheduling the CCR that we do not want to lose TOCICO 2006 Conference 1. Being able to tie the Rope so that the CCR will not starve and will not waste its capacity • Exploiting the CCR capacity 2. Being able to know whether the delivery dates, which we get from Sales, are safe • Proper subordination to the market 3. Smooth the load on the whole shop to prevent from too large temporary peaks of load • Enabling the full subordination of the non-constraints 3 © 2006 TOCICO. All rights reserved.
  • 4. Finite capacity scheduling of the CCR Is the focus absolutely right? TOCICO 2006 Conference • The focus of Operations is on the exploitation of the capacity of the CCR − Many times it leads to problematic subordination to the market − Orders that have relatively low T/CU are pushed forward in time − The identity of the client and the impact on the reputation are not always taken into consideration − There is a huge difficulty to deal with urgent orders − A policy of “adherence to the CCR schedule” makes it difficult to enter changes caused by customers who have new priorities − The result is that the response to the market demand lacks flexibility 4 © 2006 TOCICO. All rights reserved.
  • 5. Finite capacity scheduling of the CCR Is it right for make-to-stock? TOCICO 2006 Conference • The need for better flexibility is especially noted in orders that are made to stock − Because the true priority of a stock order is not known at the time of the scheduling − The priority of stock orders depends on the finished goods stock versus the demand. This could change in a day • The current practice is to assign a date to the stock order and then base the CCR schedule on that date, like any make-to-order − The date is based on forecast − Many times the derived priorities of the schedule are wrong 5 © 2006 TOCICO. All rights reserved.
  • 6. Finite capacity scheduling of the CCR Three buffers to maintain TOCICO 2006 Conference • The CCR detailed schedule forces three different buffers to be implemented, without good priority mechanism between them − The Shipping Buffer protects the due-dates − The CCR Buffer protects the detailed schedule − The Assembly Buffer – controls the material release of non-CCR parts − What does it really protect? Isn’t it just an extension of the shipping buffer? 6 © 2006 TOCICO. All rights reserved.
  • 7. Finite capacity scheduling of the CCR not always simple TOCICO 2006 Conference • In certain cases the finite capacity scheduling of the CCR is especially complex − Depended setups and other technical limitations that forbid certain sequences − Time-per-batch operations, like ovens, that work on several orders together provided certain conditions apply to all orders − Many machines, which are NOT identical, are the CCR − CCR operations that feed other CCR operations • Very few, if at all, existing DBR program can handle those complexities 7 © 2006 TOCICO. All rights reserved.
  • 8. When one is used to focus on the one CCR TOCICO 2006 Conference • When the market fluctuates, even a real CCR should have periods of low load − Thus, at those times the constraint is just the market − Should we still focus on the CCR also at those times? • Sometimes the CCR shifts from one resource to another − It could be because Sales took T/CU too seriously − The equilibrium is jeopardized – all the subordination processes change − A lot of data has to be checked, maintained and fed into the DBR software − Note especially that all the buffers change! 8 © 2006 TOCICO. All rights reserved.
  • 9. Current practice of coping with the negatives TOCICO 2006 Conference • Frequent re-scheduling − Thus considering the most updated information − Alas, new problems rise from re-scheduling − A local change causes a significant change all over: − Dates promised are not safe − Frequent changes to the material release schedule could cause chaos and inferior confidence in the planning − A lot of reporting needs to be done accurately between re-scheduling 9 © 2006 TOCICO. All rights reserved.
  • 10. Some Key Observations TOCICO 2006 Conference • The market demand is a major constraint even when a capacity constraint resource is active − Failing to subordinate to the market could lead to a significant dive down of the market demand − Elevating the internal constraint won’t improve anything unless the market demand is elevated as well • In such a case how do we exploit both constraints? − Not disappointing the market − Not losing too much precious capacity of the CCR 10 © 2006 TOCICO. All rights reserved.
  • 11. The initial direction of the solution: the basic SDBR TOCICO 2006 Conference • As the market is the major constraint, let’s protect the market with just the shipping buffer − All materials are released based on due-date minus the shipping buffer − The sequence at the CCR is not planned • The less detailed is the planning the more critical is the quality of the decisions taken at the execution • The role of the execution control is now critical: dictating the right priorities on the floor 11 © 2006 TOCICO. All rights reserved.
  • 12. The initial direction of the solution: More focus on buffer management TOCICO 2006 Conference • Generally speaking every single order is given enough time to flow through the shop floor • The Rope ensures that only orders to be delivered within the shipping buffer time are released to the floor • At each work center, including the CCR, the sensible decision which order to do next depends on the state of the buffers of the relevant orders • Definition: the buffer status of the order is the percentage of the buffer consumed • The higher the buffer status is the higher the priority of the order 12 © 2006 TOCICO. All rights reserved.
  • 13. The benefits of the SDBR direction TOCICO 2006 Conference • Simpler to implement • Having just one buffer makes the priority list clear at all times • Maintaining much more flexibility to meet the changing requirements of the clients • Signals clearly that the major constraint is the market demand, thus even the CCR should subordinate to it 13 © 2006 TOCICO. All rights reserved.
  • 14. Concerns / negative branches of SDBR TOCICO 2006 Conference 1. Failing to exploit the capacity of the CCR 2. Overloading the CCR, thus causing disruption of the due-date performance 3. Maintaining too large buffers, causing some materials to be released too soon • This is the least concerning NBR and we won’t discuss it Do we agree so far? Are the above your main concerns? 14 © 2006 TOCICO. All rights reserved.
  • 15. A common basic conflict to consider TOCICO 2006 Conference B D Ensure smooth Implement a very execution and simple solution implementation A Have a successful By how much the results would be compromised working solution using the simple Conflict in place solution? C D’ Implement a Draw the best results sophisticated out of the solution solution 15 © 2006 TOCICO. All rights reserved.
  • 16. Failing to exploit the CCR capacity TOCICO 2006 Conference • Three types of miss-exploitation of the CCR 1. Starvation, meaning there is enough planned work for the CCR to do, but none of it is ready at the CCR at this time 2. The sequence at which the work arrives to the CCR forces waste of capacity of the CCR 3. The CCR works on things that are not truly needed • The third type is controlled by the master production schedule, not by the CCR schedule • The second type is relevant only when dependent setups have a major impact − In that case we need to come back to DBR, with some changes Let’s concentrate on how to prevent starvation in SDBR 16 © 2006 TOCICO. All rights reserved.
  • 17. Preventing starvation in SDBR TOCICO 2006 Conference • When the market demand is recognized as the major constraint, we expect that even the CCR be able to subordinate to the market − Ensure excellent due-date performance, even when Murphy hits the CCR itself − Be able to respond within the tolerance of the market − All the above make it necessary to maintain some protected capacity of the CCR itself − Hence, some very limited starvation does not impact the profit • The shipping buffer is usually long enough to provide enough WIP at the weakest link (the CCR) − Assuming the RoadRunner ethics is in place • The work at the CCR should be monitored daily 17 © 2006 TOCICO. All rights reserved.
  • 18. Facing the second concern: overloading the CCR TOCICO 2006 Conference • Definition: Planned load is the accumulation of the derived load on the CCR (the weakest link) of all the firm orders that have to be delivered within a certain horizon of time • The planned load is a number of hours/days − it is NOT a description of the spread of the load over time − Suppose we have only three orders in the backlog, estimated CCR time are: 50, 125 and 55 hours − The planned load is 230 hours − The sequence is not determined 18 © 2006 TOCICO. All rights reserved.
  • 19. What does the planned load tell us? TOCICO 2006 Conference • The planned load is a rough estimation of the time when the specific resource would be able to work on a new order − Assuming the resource is able to work all the time without starvation − Assuming the new order has no special priority relative to the other orders • When we monitor the planned load of the CCR we get a pretty good idea of the lead time − The planned load plus enough safety for the downstream operations 19 © 2006 TOCICO. All rights reserved.
  • 20. An example: what do we know on the environment just from what we see? TOCICO 2006 Conference • The red bar shows the planned load of 192 hours of CCR work • The green bar shows the orders already reside at the CCR site • This information is harder to get • We can easily assume the minimum safe lead time for a new order is around 240 working hours from now • Assuming 40 plus hours are more than enough from the CCR to completion • Assuming the new order could easily reach the CCR in 192 hours 20 © 2006 TOCICO. All rights reserved.
  • 21. The difference between a finite-capacity schedule and the planned load TOCICO 2006 Conference • On the face of it the planned load is a schedule − It is similar to “forward loading” process − But, there is no sophistication in the sequence of orders − No efforts are done to validate the material would really arrive to the CCR on the time predicted by the planned load − The planned load should not be treated as a schedule – it should not dictate any sequence the operator has to follow • The most important asset of the planned load is the rough determination of the time a new order has to wait for the CCR 21 © 2006 TOCICO. All rights reserved.
  • 22. Dealing with the overloading concern TOCICO 2006 Conference • The planned load of the CCR, at any given time, should be compared to the standard lead time required by the market − Certainly we expect the planned load to be LESS than the standard lead-time • There is, yet, no guaranty that the load on the CCR would be smooth − A cluster of orders to be shipped at the same date could be problematic • We need to take another step and control the promised dates of deliveries according to the CCR’s planned load 22 © 2006 TOCICO. All rights reserved.
  • 23. Promising delivery dates based on the planned load TOCICO 2006 Conference • In order to achieve reliable delivery dates Sales and Operations must synchronize their actions • Instead of Sales promising delivery dates and then Operations trying to meet as many of the dates as possible, let’s build a mechanism to determine the dates that Operation can commit to deliver • As the planned load is a rough estimation of the time a new order would be processed by the CCR, we should add a time buffer to the planned load and get a “safe delivery date” for the order − Let’s decide to add ½ of the total shipping buffer 23 © 2006 TOCICO. All rights reserved.
  • 24. This is how it looks like TOCICO 2006 Conference All the required CCR load for the orders that have a committed delivery date have been accumulated here Daily 50% of buffer We can Load safely deliver here The planned load Time (days) 24 © 2006 TOCICO. All rights reserved.
  • 25. And this is how we tie the Rope to the Planned Load TOCICO 2006 Conference 50% of buffer 50% of buffer Daily We can Load safely deliver here full buffer Release point Time (days) The same approach, assuming the new order would be processed roughly at the current planned load time, leads us also to release the raw materials at half of the total shipping buffer before that time. All in all we have a full buffer between the release and delivery 25 © 2006 TOCICO. All rights reserved.
  • 26. The dilemma of quoting short lead-times TOCICO 2006 Conference • When the planned load is close to the standard lead-time or longer, then we know we must quote the safe date • But, what happens when the safe-date is much shorter than the standard quoted lead-time? Should we quote short quoted lead times whenever possible? • On one hand we could attract more clients now • On the other hand, the clients would expect those short deliveries as the regular service also in the future and for the same price 26 © 2006 TOCICO. All rights reserved.
  • 27. The dilemma of quoting short lead-times TOCICO 2006 Conference • The solution is offering a service of very fast deliveries for a considerable markup, while keeping the regular prices for standard time, but fully reliable, deliveries • Then we have to deal with orders with very short lead-time, while the regular orders have much longer lead-times − We’ll handle the negative ramifications, already mentioned earlier, later in the presentation 27 © 2006 TOCICO. All rights reserved.
  • 28. The shipping buffer when the safe date is earlier than the quoted lead time TOCICO 2006 Conference Daily Safe Load delivery Addition to full buffer the buffer We promise standard release lead time point Standard lead time Time (days) The actual shipping buffer for this order is expanded from the release date, dictated by the planned load minus half of the original buffer, until the formal date for the regular price 28 © 2006 TOCICO. All rights reserved.
  • 29. Points of discussion so far TOCICO 2006 Conference • Assuming dependent setups are not significant, what are the negative branches of using SDBR in general? − Would DBR work better? At what situations? − Do we need more injections to make SDBR (one buffer planning) work properly? • How should we treat quoting times that are later than the internal safe-date? − Should we keep the shipping buffer fixed and release the materials accordingly? − We thus force idle time on the weakest link. What are the possible ramifications? 29 © 2006 TOCICO. All rights reserved.
  • 30. The complication of depended setups TOCICO 2006 Conference • Depended setups means significant dependency of the setup time on the previous product processed at the specific resource • The first question to raise: if the machine would process according to an arbitrary sequence, would it become a true bottleneck? − If the answer is NO, then there is no problem whatsoever to implement SDBR/BM without distortion − Many times it is worthwhile to invest in adding capacity, or coming up with engineering innovation, to get rid of the negative impact of dependent setups − Otherwise we have you yield to a preferred sequence imposed by the dependent setups 30 © 2006 TOCICO. All rights reserved.
  • 31. Regarding dependent setups TOCICO 2006 Conference • It could be the case that the preferred sequence is dictated by another resource – not the CCR • A preferred sequence is not necessarily a well- defined unique sequence, but a general sequence between families of items that within the family the setup is relatively short • The assumption is that violating the sequence would turn the resource into a bottleneck − Certainly we need to consider a situation where few violations of the sequence would not create a bottleneck 31 © 2006 TOCICO. All rights reserved.
  • 32. Dealing with dependent setups: two main approaches TOCICO 2006 Conference • In a situation where we cannot afford an arbitrary sequence on the CCR, like in dependent setups, two optional approaches should be checked 1. The shipping buffer is long enough to provide enough choice for the foreman, considering the priorities of the orders − In this case SDBR is still the preferable method 2. A fixed sequence determined for the CCR ahead of time, which is protected by a CCR buffer − Note that what is critical point is the sequence, NOT the exact quantity to be produced! 32 © 2006 TOCICO. All rights reserved.
  • 33. Dealing with more than one standard lead time TOCICO 2006 Conference • Defining the problem: When a company has different commitments to lead times, then promising reliable due-dates is problematic because not all the orders are known at the time • This problem includes different categories: 1. The Rapid Response viable vision template 2. Commitment to a strategic client to fast response 3. Maintaining product mix with highly variable standard lead times in the industry 4. Items that are make to stock 33 © 2006 TOCICO. All rights reserved.
  • 34. Reserving capacity for the faster items TOCICO 2006 Conference Only this portion is free for allocation to normal orders Reserved Super fast Fast Standard lead time The proposed approach is to dedicate certain percentage of the capacity for the faster response items. The calculation of the planned load for determining the safe dates is now based on (100 – ReservedPercentage) of the available capacity 34 © 2006 TOCICO. All rights reserved.
  • 35. Managing the reserved capacity TOCICO 2006 Conference • How much reserved capacity we need? − Like in the determination of buffer size a good initial guess is all we can hope for − Then, we need to look for a way to assess whether the current reservation level is about right 35 © 2006 TOCICO. All rights reserved.
  • 36. What do we lose from determining a too high reservation level? TOCICO 2006 Conference • Do we lose precious CCR capacity when we have reserved too much capacity for the “special” items? − We do not really mean that every day the CCR will work X% on the special orders and (100-x)% on regular orders − The CCR should work on whatever is available, taking into account the buffer statuses − Thus, when there is not much work for the special orders, then most regular orders would be processed earlier than predicted − We are not going to move the due-dates backwards in time − But, it is easy to move the release of materials backwards when it is evident the CCR would be able to process them earlier 36 © 2006 TOCICO. All rights reserved.
  • 37. What do we lose from determining a too high reservation level? TOCICO 2006 Conference • When we plan with high reservation of capacity the safe-dates are too conservative • So, when the safe-dates lie beyond the standard lead-time, we might lose market demand • Then we lose something substantial, which makes it worth to re-check the amount of reservation 37 © 2006 TOCICO. All rights reserved.
  • 38. What happens when the reservation level is too low? TOCICO 2006 Conference • The high number of special orders would push the completion of regular orders later in time − As long as the calculated safe dates for regular orders are far from the standard lead times the situation is under control − When the buffers of the regular order are not extended, then more regular orders are pushed into the red, and the number of red orders rises sharply − Then there is a need to increase the reservation level, causing the safe dates to be later in time, possibly causing losing some sales 38 © 2006 TOCICO. All rights reserved.
  • 39. Tools for managing the reservation level TOCICO 2006 Conference • Monitoring the two parts of the planned load − The first part is the regular planned load, consisting of all the regular commitments, and how the front of the planned load stands relative to the standard lead time − The second part contains the special orders assuming only the reserved capacity is available for them and how close they are to the short lead-times references 39 © 2006 TOCICO. All rights reserved.
  • 40. Tools for managing the reservation level TOCICO 2006 Conference • Eventually we need to control the overall capacity and how it is used for both regular and special orders • For that we need full planned load for the shortest lead-time (like super-fast) − All the orders that need to be worked on within the short lead time − The planned load needs to show some excess capacity within the short time frame 40 © 2006 TOCICO. All rights reserved.
  • 41. Main Discussion TOCICO 2006 Conference • The planned load as a major planning tool (dictating due- dates) − Effectiveness and how accurate it has to be? − Ways of calculating the planned load (with or without setups and maintenance) − After how many resources we need to monitor their planned load? • The planned load as support to execution decisions (temporary increase of buffer) − How does the planned load interact with buffer management? • When the safe-date is much earlier than standard – why extending the buffers? If so, why not extend just the green? • Other questions / reservations 41 © 2006 TOCICO. All rights reserved.