2. ► French language acronym
► Stands for:
“Federation Internationale Des Ingenieurs-Conseils”
► Web Site : www.fidic.org
► Established in Switzerland in 1913, Based in Geneva
► Formed by three national associations of consulting Engineers ( Belgium, France & Switzerland )
► Expended in 1945 to include 40 national associations.
► FIDIC now has over 100 members countries
► FIDIC provides standard forms of consulting contract
► Published first conditions of contract in 1957
► Under this umbrella 30,000 firms & 1000,000 professionals are represented.
Background
3. Rainbow Suit
2nd Edition (2017) (1st Edition 1999)
Construction Contract – Red Book (2017)
Plant and Design-Built Contract – Yellow
Book (2017)
EPC/Turnkey contract – Silver Book ( 2017)
Other Contracts
Short Form - Green Book (1999)
MDB construction contract - Pink Book (3rd
Ed 2010)
DBO – Gold Book (2008)
Dredgers Contract – Purple Book
Client consultant model services
Agreement – White Book (2017)
FIDIC Standard Forms
4. Contract Books & Format
Over the year FIDIC has consistently improved on its contracts
Add some new forms of contract and updated new once
Red Book
► Conditions of contract for construction of Building & Engineering works, designed
by the employer.
► FIDIC claim, red book is the mostly widely used international construction contract
► The accepted Contract amount is based on estimated quantities.
► Engineer will also responsible for monitoring the construction work & certifying
payments
► 1st edition in 1999
5. Yellow Book
► Conditions of contract for construction for plant & design built projects,
designed by the contractor (worker)
►Engineer will administrator the contract
►Contractor is responsible for executing of building or engineering works
►Lump sum price
► 1st edition 1999
Pink Book
► Harmonized Red Book (MDB Edition)
►conditions of contract for construction for building and engineering works
designed by employer
►Multilateral Development Banks are provide finance
►Islamic development & world bank worked with FIDIC
►(version 3, 2010) Pink Book replaced earlier editions from 2005 and 2007.
6. Silver Book
Gold Book
► Conditions of contract for design, built & operate projects
► Operate & maintained by contractor long -term
► Has 2 phases:
1. Design-Build phase
2. An Operation Service Phase
► Contractor has NO responsibility for either financing the project or for
ultimate commercial success
► 1st edition 2008
► Conditions of contract for plant & design for EPC & Turnkey projects
► Contractor responsible for all activities (Design, Procurement & Construction)
► Majority of risks are allocated to the Contractor
► A Turnkey responsibility
► Used in International Infrastructure Projects.
► Completion Risk
► 1st edition 1999
7. ► First book design & built contract released by FIDIC
► Drafted for use where the contractor carries total reliability for designs’
► Conditions of contract for Design built and Turnkey
► First published in 1995
► Relatively small contract value ( say under $500,000 )
► Short construction time ( say less than 6 months )
► Simple or repetitive work ( e.g. dreding work )
► No Engineer
► 1st Edition 2006
Green Book
Orang Book