2. TABLE OF CONTENTS
One Room Building
Concrete work in foundation (Center line and
separate wall method)
Brickwork in footing (Center line and separate wall
method)
Brickwork in walls (Center line and separate wall
method)
Two Rooms Building
Concrete work in foundation (Center line and
separate wall method)
5. 0.9 m
5.3m
4.3 m
Total Center line = 5.3+5.3+4.3+4.3=19.2 m
Width = 0.9 m Total Qty of concrete in foundation= (19.2×0.9×0.3) cum
Center Line Method
6. 0.9 m
5.3m
6.2m
4.3 m
3.4 m
Separate Wall Method
Width = 0.9 m Total Qty of concrete in fdn= (2×6.2×0.9×0.3) + (2×3.4×0.9×0.3)cum
Long Wall = 5.3+0.9=6.2 m Short Wall = 4.3-0.9=3.4 m
7. 0.6 m
5.3m
4.3 m
Total Center line = 5.3+5.3+4.3+4.3=19.2 m
Width = 0.6 m Total Qty of brickwork in Ist footing= (19.2×0.6×0.3) cum
Center Line Method
8. 0.6 m
5.3m
5.9 m
4.3 m
3.7 m
Width = 0.6 m
Separate Wall Method
Long Wall = 5.3+0.6=5.9 m Short Wall = 4.3-0.6=3.7 m
Total Qty of brickwork in Ist footing= (2×5.9×0.6×0.3) + (2×3.7×0.6×0.3)cum
9. 5.3m
4.3 m
0.3 m
Total Center line = 5.3+5.3+4.3+4.3=19.2 m
Width = 0.3 m Total Qty of brickwork in walls= (19.2×0.3×3.5) cum
Center Line Method
10. 5.6 m
5.3m
4.3 m
4 m
0.3 m
Width = 0.3 m
Separate Wall Method
Long Wall = 5.3+0.3=5.6 m Short Wall = 4.3-0.3=4.0 m
Total Qty of brickwork in walls= (2×5.6×0.3×3.5) + (2×4.0×0.3×3.5)cum
13. Center Line Method
Total Center line = 5.3+5.3+5.3+5.3+4.3+4.3+4.3=34.1 m
Width = 0.9 m Total Qty of concrete in fdn= (34.1×0.9×0.3)
5.3m 5.3m
4.3 m
0.9 m
Intermediate wall
– (2×0.9×(0.9/2) ×0.3)cum
14. Separate Wall Method
Long Wall = 5.3+5.3+0.9=11.5 m Short Wall = 4.3-0.9=3.4 m
Width = 0.9 m Total Qty of concrete in fdn= (2×11.5×0.9×0.3)
5.3m 5.3m
4.3 m
0.9 m
11.5 m
3.4m
Intermediate wall
+ (3×3.4×0.9×0.3)cum