SlideShare una empresa de Scribd logo
1 de 117
Descargar para leer sin conexión
David H Moloney
14th August 2016
Sea Port Construction, Project Execution Plan
Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled.
Also the measures to ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant
and Sequence to construct a Sea Port .
This presentation can be used to engage Stakeholders and to get the Site Teams
commitment to the programme. Also can be used for Induction Training and as a
way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and
controlled.
High in Educational Value and easily understood. Recommended for Continuing
Professional Development (CPD)
This Video Presentation is innovative and has many beneficial uses.
Video https://www.youtube.com/watch?v=6_Aco_GPO8I
Contents
ⓒ David H Moloney
Introduction
Quay Wall
QuayWall
Quay Wall
QuayWall
Brief Description
The quay wall is constructed using precast reinforced concrete hollow
blocks that weigh up to 160 tonnes. The blocks were cast in the on-site
precast yard and loaded onto barges at the temporary loading jetty that
had a 200 tonne capacity gantry crane.
A screeding frame that extended from the sea bet to above water was
used to place the bedding layer to the correct level.
Up to 22 blocks were placed per day using a barge with a crane.
Part of the coping beam was cast in-sit-u in sections using concrete pumps
positioned on the reclaimed land behind the quay wall.
Sequence & Methods to Construct Quay Wall
QuayWall
3D Animation
Quay-wall
ⓒ David H Moloney
Placing Precast Quay Blocks Placing Precast Quay Blocks
Screed Frame for preparing Granular Foundation Placing Precast Quay Blocks
Quay Wall Beam
Screed Frame
Miscellaneous
Brief Description
Duqm, Oman
Mooring Bollards & Marine Fenders
Miscellaneous
Marine Equipment ⓒ David H Moloney
Drawing – Quay Wall Cross Section
Breakwater & Wavewall
Breakwater&Wavewall
Breakwater & Wavewall
Breakwater&Wavewall
Brief Description
The breakwater is constructed using core rock, rock armour, precast
armour units and geotextile.
The core rock is placed using split hopper barges in deep water and
by lorry tipping and dozers in shallow water where the risk of
slippage is minimal.
The precast armour units are placed using crawler cranes fitted with
a real-time visual aid system that enabled 70 placements per day.
The wave wall is cast in-sit-u in 6 metre long sections.
Sequence & Methods to Construct Breakwater & Wavewall
Breakwater&Wavewall
Breakwaters
ⓒ David H Moloney
Filling Barge with Rock – Temporary Jetty Placing Rock Fill
Breakwater under Construction Placing Rock Armour
Breakwaters
Placing Rock Fill
Breakwater under Construction
Barges for Rock Fill
Geotextile
Precast Sea Armour
Placing Armour
Rock Sea Armour
Placing Armour
Sea Wall
Drawing – Breakwater Cross Section
Quarry Run Rock Fill
Drawing – Breakwater Cross Section
Quarry Run Rock Fill
Wave Wall
Geotextile
Rock Armour 0.5 - 1 ton
Precast Armour
Rock Armour 1 - 3 ton
Precast Yard & Loading Jetty
PrecastYard&LoadingJetty
Precast Yard & Loading Jetty
PrecastYard&LoadingJetty
Brief Description
Full-scale sample castings are constructed to demonstrate and
document that all the requirements of the concrete and the
execution of the work are fulfilled using the actual methods and
performed by personnel that will carry out the future castings. One
concrete component of each type is produced for approval. The
approved castings were retained in a dedicated area for quality
assurance purposes.
All works were inspected in accordance with the Inspection & Test
Plan on an ongoing basis, in accordance with the site Project Quality
Plan. The ITP set out in matrix form the sequence of inspection
steps, the governing document (specification, standards), the
standard to be achieved, the persons witnessing and the supporting
documents to be produced.
Precast Yard & Loading Jetty
PrecastYard&LoadingJetty
Precast Yard & Loading Jetty
PrecastYard&LoadingJetty
Precast Yard & Loading Jetty
PrecastYard&LoadingJetty
Pre-casting Quay Blocks
Precast Sea Armour
Shutters for Precast Sea Armour Shutters for Precast Sea Armour
Quarry & Aggregate Production
3D image to show Sequence, Method & Plant.
ⓒ David H Moloney
Quarry
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
Concrete Batching Yard
Silos, Ice Flake Plant, Chilled water, Mixer
Storage bays for aggregates
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
Vibrating Concrete
ⓒ David H Moloney
Concrete
Dredging & Reclamation
Dredging&Reclamation
Dredging & Reclamation
Dredging&Reclamation
Brief Description
Dredgers are marine vessels used to excavate and fill under water.
Types
1. Cutter Suction Dredgers are used to dredge hard soils by cutting
and breaking up the soil using a rotating head at the end of a pipe
which is lowered onto the sea bed. The fragmented material is
sucked and pumped either into a hopper barge or through a floating
pipeline. During operation the dredger is anchored by a spud that
allows the cutting head to swing in an arc.
2. Trailing Suction Hopper Dredgers are used to dredge soft and
loose soils, gravels and silts. There are two suction drag heads
which are lowered onto the sea bed. These move with the dredger
along the sea bed. The dredged material is sucked and pumped
either into the hopper or through a floating pipeline to a discharge
area.
Dredging & Reclamation
Dredging&Reclamation
Dredger - Trailing Suction
Dredging&Reclamation
Boskalis Netherlands
Dredger - Cutter Suction
Dredging&Reclamation
Boskalis Netherlands
Dredger - Backhoe
Dredging&Reclamation
Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Vibro Compaction - Fill behind Quay
Vibro Compaction - Fill behind Quay
Ground Improvement using deep vibro-compaction.
Purpose is to provide protection against liquefaction during a seismic
event. Also to provide a specified minimum ground bearing capacity.
Vibro-compaction was use to compact the Dubai man made islands
that were constructed from dredged sand.
Equipment.
Vibroflot with extension tube, hydraulic power pack mounted on crane,
diesel engine driven water jetting pumps, compressors, crawler cranes
60 tonne capacity, water tank, de-watering pump
Vibro Compaction - Fill behind Quay
3D image to show Sequence, Method & Plant.
David H Moloney
ⓒ David H Moloney
Vibro Compaction
VibroCompaction
Surveying&settingOut
Survey & Setting Out
Surveying&settingOut
Brief Description
Ope
Survey & Setting Out
Survey Tower
Setting out & Surveying
Setting out & Surveying
Port Operation
PortOperation
Port Operation
PortOperation
Port Operation
PortOperation
Port Operation
PortOperation
Site Facilities & Temporary Works
SiteFacilities&temporaryWorks
Site Facilities & Temporary Works
SiteFacilities&temporaryWorks
Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Site Hoarding examples
ⓒ David H Moloney
GeneralItems
Wheel Wash Drive-through
ⓒ David H Moloney
GeneralItems
Wheel Wash Drive-throughGeneralItems
Temporary Electricity Supply & Tower Lights
Generators
GeneralItems
Dewatering
ⓒ David H Moloney
GeneralItems
Concrete Batching Yard 3 Nr MixersGeneralItems
Health, Safety & Environmental
Health,safety&environmental
Emergency Phone Numbers & Response
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Site Safety Posters examples
Safety Precautions
Personal Protective Equipment (PPE)
Health,Safety&Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
Safety Training on Site
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Safety Training Matrix
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Emergency Response Drill
HSE
Drills and exercises are used to rehearse anticipated emergency scenarios
Environmentally Friendly Site Air, Noise, Water & Soil Pollution
Hazardous Substances Symbols
Health,Safety&Environment
COSHH stands for the
Control of Substances
Hazardous to Health
Shown are the new
hazard symbols
Water Pollution PreventionGeneralItems
Segregation of WasteHealth,Safety&Environment
Segregation of waste for proper disposal and
recycling. Less waste goes to landfill and
hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Putting Waste Concrete to use
ⓒ David H Moloney
Health,Safety&Environment Precast bases for signs and hoarding,
Precast blocks for walls.
Administration
Administration
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Staff Responsibility Matrix
Staff Directory
Brief Description
List of staff and their
contact details
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
Quotations Comparison Sheet
Filing System
Quality Assurance
QualityAssurance
Quality Assurance Dashboard Dashboard is a single page, graphical representation of
current statistics and historical trends
Laboratory
ⓒ David H Moloney
AsphaltPaving
Programme & Progress Monitoring
Programme&ProgressMonitoring
Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
Histogram Charts for Resources & Outputs
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Other Projects
OtherProjects
Brief Description
Jetty for Kuwait Causeway
Other Projects
Jetty for Kuwait Causeway
Other Projects
Brief Description
Concrete Batching Plant on Barge.
Kuwait Causeway
Other Projects
Kuwait Causeway Offshore Piling
Other Projects
Concrete Batching Plant on Barge. Kuwait Causeway
Other Projects
Pile Driving
Other Projects
Temporary Bridge
Other Projects
Temporary Bridge Piling
Other Projects
Brief Description
Marine Piles
Other Projects
Brief Description
Screed Frame. Morocco
Other Projects
Brief Description
Quay Wall Ruwais UAE
Other Projects
Brief Description
Dubai Palm Island, Rock Armour
Other Projects
Brief Description
Dubai Creek, strengthen
quay wall with sheet piles and
ground anchors
Other Projects
Brief Description
Abu Dhabi Quay Wall
Other Projects
Brief Description
St. Croix Bridge
Other Projects
Brief Description
Cofferdams examples
Other Projects
Jebel Ali DubaiOther Projects
Jebel Ali Dubai
Ports
Muscat Omani
Dublin Cork
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
My Port Construction YouTube link https://www.youtube.com/watch?v=6_Aco_GPO8I

Más contenido relacionado

La actualidad más candente

Design of simple beam using staad pro
Design of simple beam using staad proDesign of simple beam using staad pro
Design of simple beam using staad proSHAMJITH KM
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623VATSAL PATEL
 
Bridge construction methodology
Bridge construction methodologyBridge construction methodology
Bridge construction methodologyELSAYED DIAB
 
Classification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxClassification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxJAYA LAKSHMI ATHRAM
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
 
Vertical wall type breakwaters
Vertical wall type breakwatersVertical wall type breakwaters
Vertical wall type breakwatersVikas Patre
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623VATSAL PATEL
 
Harbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT MysoreHarbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT MysoreShankaregowda Mandya
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Dams & its Construction
Dams & its ConstructionDams & its Construction
Dams & its ConstructionZakaria Yahya
 
CONSTRUCTION CONVEYER EQUIPMENTS.
CONSTRUCTION CONVEYER EQUIPMENTS.CONSTRUCTION CONVEYER EQUIPMENTS.
CONSTRUCTION CONVEYER EQUIPMENTS.Nihal Abidi
 
Breakwaters and types
Breakwaters and types Breakwaters and types
Breakwaters and types M Aamer Raza
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 
Type of caissons
Type of caissonsType of caissons
Type of caissonsAB MAKASANA
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623VATSAL PATEL
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt1971995
 
harbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionharbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionHasna Hassan
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenenceGhanashyam Prajapati
 

La actualidad más candente (20)

Formwork
FormworkFormwork
Formwork
 
Design of simple beam using staad pro
Design of simple beam using staad proDesign of simple beam using staad pro
Design of simple beam using staad pro
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
 
Bridge construction methodology
Bridge construction methodologyBridge construction methodology
Bridge construction methodology
 
Classification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxClassification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptx
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
Vertical wall type breakwaters
Vertical wall type breakwatersVertical wall type breakwaters
Vertical wall type breakwaters
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
 
Harbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT MysoreHarbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT Mysore
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Dams & its Construction
Dams & its ConstructionDams & its Construction
Dams & its Construction
 
CONSTRUCTION CONVEYER EQUIPMENTS.
CONSTRUCTION CONVEYER EQUIPMENTS.CONSTRUCTION CONVEYER EQUIPMENTS.
CONSTRUCTION CONVEYER EQUIPMENTS.
 
Breakwaters and types
Breakwaters and types Breakwaters and types
Breakwaters and types
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
Type of caissons
Type of caissonsType of caissons
Type of caissons
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
harbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introductionharbour and dock engineering ppt 01 introduction
harbour and dock engineering ppt 01 introduction
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 

Destacado

Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution PlanDavid H Moloney
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanDavid H Moloney
 
Horbour & Dock Engineerin
Horbour & Dock EngineerinHorbour & Dock Engineerin
Horbour & Dock Engineerinjamalkhan619
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution ProcessC K Vishwakarma
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionDavid H Moloney
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 kmDavid H Moloney
 
Breakwater, jetties and groins.
Breakwater, jetties and groins.Breakwater, jetties and groins.
Breakwater, jetties and groins.Latif Hyder Wadho
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction MethodsDavid H Moloney
 
Concept & Construction of PALM ISLAND
Concept & Construction of PALM ISLANDConcept & Construction of PALM ISLAND
Concept & Construction of PALM ISLANDJASHU JASWANTH
 
Palm island Construction with Management 5 Ms
Palm island Construction with Management 5 MsPalm island Construction with Management 5 Ms
Palm island Construction with Management 5 MsGargi Kapadia
 
Port and Harbor Engineering
Port and Harbor EngineeringPort and Harbor Engineering
Port and Harbor EngineeringJerome Jaime
 
Port operations & management slideshow
Port operations & management slideshowPort operations & management slideshow
Port operations & management slideshowVijay Hiranandani
 

Destacado (20)

Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
India :Ports Sector Report_August 2013
India :Ports Sector Report_August 2013India :Ports Sector Report_August 2013
India :Ports Sector Report_August 2013
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Horbour & Dock Engineerin
Horbour & Dock EngineerinHorbour & Dock Engineerin
Horbour & Dock Engineerin
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 km
 
Breakwater, jetties and groins.
Breakwater, jetties and groins.Breakwater, jetties and groins.
Breakwater, jetties and groins.
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 
Concept & Construction of PALM ISLAND
Concept & Construction of PALM ISLANDConcept & Construction of PALM ISLAND
Concept & Construction of PALM ISLAND
 
Breakwaters
BreakwatersBreakwaters
Breakwaters
 
Palm island Construction with Management 5 Ms
Palm island Construction with Management 5 MsPalm island Construction with Management 5 Ms
Palm island Construction with Management 5 Ms
 
Port and Harbor Engineering
Port and Harbor EngineeringPort and Harbor Engineering
Port and Harbor Engineering
 
Breakwaters
BreakwatersBreakwaters
Breakwaters
 
Port operations & management slideshow
Port operations & management slideshowPort operations & management slideshow
Port operations & management slideshow
 

Similar a Sea Port Construction, Project Execution Plan

Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport ConstructionDavid H Moloney
 
Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction DetailsDavid H Moloney
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction ExplainedDavid H Moloney
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDavid H Moloney
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsMohamed Elnagar
 
NEWS PAPER Bay area Observer
NEWS PAPER Bay area ObserverNEWS PAPER Bay area Observer
NEWS PAPER Bay area ObserverMike McClure
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015Blase Townsing
 
Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1amrhaggag
 
underwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptxunderwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptxSaffanAhmed1
 
WY Offshore segments
WY Offshore segmentsWY Offshore segments
WY Offshore segmentsAlfred Hong
 
Project Management of M&E works at a WwTW
Project Management of M&E works at a WwTWProject Management of M&E works at a WwTW
Project Management of M&E works at a WwTWftwg
 
Turnkey M&E Installation Ww Tw
Turnkey M&E Installation Ww TwTurnkey M&E Installation Ww Tw
Turnkey M&E Installation Ww Twftwg
 
Oil and gas industry 1.1
Oil and gas industry 1.1Oil and gas industry 1.1
Oil and gas industry 1.1Jorge De Brito
 
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSDEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSiQHub
 

Similar a Sea Port Construction, Project Execution Plan (20)

Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction Details
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction Explained
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in Tunnels
 
Chinmoy Pathak Choudhury_LTV Internship report
Chinmoy Pathak Choudhury_LTV Internship reportChinmoy Pathak Choudhury_LTV Internship report
Chinmoy Pathak Choudhury_LTV Internship report
 
GEM - EMW Company Profile
GEM - EMW Company ProfileGEM - EMW Company Profile
GEM - EMW Company Profile
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
 
NEWS PAPER Bay area Observer
NEWS PAPER Bay area ObserverNEWS PAPER Bay area Observer
NEWS PAPER Bay area Observer
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015
 
Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1Intro to oil well drilling ops pt 1
Intro to oil well drilling ops pt 1
 
underwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptxunderwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptx
 
Petroleum drilling fundamentals
Petroleum drilling fundamentalsPetroleum drilling fundamentals
Petroleum drilling fundamentals
 
WY Offshore segments
WY Offshore segmentsWY Offshore segments
WY Offshore segments
 
How are sea ports constructed?
How are sea ports constructed?How are sea ports constructed?
How are sea ports constructed?
 
Project Management of M&E works at a WwTW
Project Management of M&E works at a WwTWProject Management of M&E works at a WwTW
Project Management of M&E works at a WwTW
 
Turnkey M&E Installation Ww Tw
Turnkey M&E Installation Ww TwTurnkey M&E Installation Ww Tw
Turnkey M&E Installation Ww Tw
 
Oil and gas industry 1.1
Oil and gas industry 1.1Oil and gas industry 1.1
Oil and gas industry 1.1
 
Advance Prestress Bridge
Advance Prestress BridgeAdvance Prestress Bridge
Advance Prestress Bridge
 
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSDEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
 
Nykilde geoweb slope design package
Nykilde geoweb slope design packageNykilde geoweb slope design package
Nykilde geoweb slope design package
 

Más de David H Moloney

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 David H Moloney
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824David H Moloney
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pagesDavid H Moloney
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pagesDavid H Moloney
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionDavid H Moloney
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside ConstructionDavid H Moloney
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTERDavid H Moloney
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationDavid H Moloney
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageDavid H Moloney
 

Más de David H Moloney (14)

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside Construction
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulage
 

Último

Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Communityprachaibot
 

Último (20)

Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Community
 

Sea Port Construction, Project Execution Plan